11239 W MONTANA AVE 90049
Certificate Information: 11239 W MONTANA AVE 90049
- Application / Permit
- 21047-20000-01565
- Plan Check / Job No.
- B21VN08715
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL/ ENLARGE (E) SWIMMING POOL ADD NEW SPA PER STANDARD PLAN #268 AND ENGINEER DETAILS.
- Permit Issued
- Issued on 11/22/2021
- Issuing Office
- Current Status
- CofO Issued on 9/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2021 | ROSENDO MEDINA |
| Corrections Issued | 7/17/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 8/18/2021 | ROSENDO MEDINA |
| Plan Check Approved | 9/13/2021 | ROSENDO MEDINA |
| Building Plans Picked Up | 9/14/2021 | APPLICANT |
| Issued | 11/22/2021 | APPLICANT |
| CofO in Progress | 9/1/2022 | CARLOS MATAMOROS |
| Permit Finaled | 9/3/2022 | DANIEL ORRANTE |
| CofO Issued | 9/3/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/3/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/3/2021 | BRIAN MILLER |
Contact Information
| Contractor | 3a Genius Remodeling Corp; Lic. No.: 1005832-B | 23012 GILMORE STREET WEST HILLS, CA 91307 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/8/2021 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 12/16/2021 | Corrections Issued | CARLOS MATAMOROS |
| Grounding or Bonding | 12/16/2021 | Approved | CARLOS MATAMOROS |
| Pool Piping | 12/16/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Gunite | 12/16/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 12/20/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Grounding or Bonding | 12/20/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Gunite | 12/20/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Rough-Plumbing | 12/20/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 12/27/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Grounding or Bonding | 12/27/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Pre-Gunite | 12/27/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Rough-Plumbing | 12/27/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Gunite | 2/14/2022 | Approved | CARLOS MATAMOROS |
| Pool Piping | 2/14/2022 | Corrections Issued | CARLOS MATAMOROS |
| Pre-Gunite | 2/14/2022 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 2/14/2022 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 2/14/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Grounding or Bonding | 2/18/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pool Piping | 2/18/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Rough-Plumbing | 2/18/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Grounding or Bonding | 2/22/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Pool Piping | 2/22/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Rough-Plumbing | 2/22/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Grounding or Bonding | 2/24/2022 | Approved | CARLOS MATAMOROS |
| Pool Piping | 2/24/2022 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 2/24/2022 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 8/16/2022 | Approved | CARLOS MATAMOROS |
| Final | 8/25/2022 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 8/25/2022 | SGSOV Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/30/2022 | Approved | CARLOS MATAMOROS |
| Final | 8/30/2022 | OK to Issue CofO | CARLOS MATAMOROS |