12444 W VENICE BLVD 90066
Certificate Information: 12444 W VENICE BLVD 90066
- Application / Permit
- 21047-20000-01548
- Plan Check / Job No.
- B21VN08618
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- Apartment
- Primary Use
- (4) Pool/Spa - Public
- Work Description
- (N) METAL FRAMED PUBLIC SPA (22' X 10') ON 6TH FLOOR OF (E) APT BLDG PER ENG'R DESIGN
- Permit Issued
- Issued on 2/7/2022
- Issuing Office
- Current Status
- CofO Issued on 3/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 7/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/10/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 8/13/2021 | STEVEN KIM |
| Building Plans Picked Up | 9/21/2021 | APPLICANT |
| Plan Check Approved | 12/16/2021 | NILOOFAR MEHRAIN |
| Issued | 2/7/2022 | APPLICANT |
| CofO in Progress | 1/10/2023 | DERRICK SPENCER |
| Permit Finaled | 3/10/2023 | HENRY BAGHDASSARIAN |
| CofO Issued | 3/10/2023 | HENRY BAGHDASSARIAN |
| Permit Finaled | 3/10/2023 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Public Swimming Pool approval | Cleared | 8/9/2021 | LACDHS APPROVED |
| Miscellaneous | Cleared | 9/23/2021 | LAUREN PADICK |
| ZA Case | Cleared | 9/23/2021 | LAUREN PADICK |
| ZA Case | Cleared | 9/23/2021 | LAUREN PADICK |
| DAS Clearance | Cleared | 11/4/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Addison Pools Inc; Lic. No.: 753417-C53 | 4363 WOODMAN AVENUE SHERMAN OAKS, CA 91423 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/11/2022 | Approved | JEFF BYTHEWAY |
| Enclosure/Fence | 10/21/2022 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 11/30/2022 | Approved | DERRICK SPENCER |
| Final | 11/30/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 1/4/2023 | OK to Issue CofO | DERRICK SPENCER |