14561 W HUSTON ST 91403
Certificate Information: 14561 W HUSTON ST 91403
- Application / Permit
- 21047-20000-01535
- Plan Check / Job No.
- B21VN08540
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 12'X20' POOL AND 7'X7' SPA PER LA STD PLAN # 268
- Permit Issued
- Issued on 6/21/2022
- Issuing Office
- Current Status
- CofO Issued on 4/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | COLIN LOREDO |
| Corrections Issued | 8/12/2021 | COLIN LOREDO |
| Quality Review Completed | 8/20/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/25/2021 | APPLICANT |
| Applicant returned to address corrections | 10/14/2021 | COLIN LOREDO |
| Plan Check Approved | 1/25/2022 | COLIN LOREDO |
| Issued | 6/21/2022 | APPLICANT |
| CofO in Progress | 4/14/2025 | JAVIER RAMOS JR |
| Permit Finaled | 4/29/2025 | RUBEN SALAS |
| Permit Finaled | 4/29/2025 | RUBEN SALAS |
| CofO Issued | 4/29/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/18/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Express Remodeling And Plumbing; Lic. No.: 919808-B | P O BOX 4371 BURBANK, CA 91503 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/17/2024 | Corrections Issued | JACK KARGODORIAN |
| Pre-Gunite | 5/20/2024 | Approved | JACK KARGODORIAN |
| Deputy Shotcrete | 5/23/2024 | Conditional Approval | ROBERT GOLD |
| Enclosure/Fence | 9/12/2024 | Corrections Issued | JACK KARGODORIAN |
| Enclosure/Fence | 10/24/2024 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 12/9/2024 | Approved | JACK KARGODORIAN |
| Final | 12/9/2024 | Corrections Issued | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Approved | JACK KARGODORIAN |
| Final | 12/23/2024 | Corrections Issued | JACK KARGODORIAN |
| Final | 12/26/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Pool Equipment Noise Test | 1/16/2025 | Approved | FELIPE PENICHE |
| Final | 4/11/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Approved | JAVIER RAMOS JR |