455 S CITRUS AVE 90036
Certificate Information: 455 S CITRUS AVE 90036
- Application / Permit
- 21047-20000-01510
- Plan Check / Job No.
- B21VN08378
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW (17'-8"x12'-0") POOL WITH (6'-0"x6'-0") SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2021 | PETER MOSESIAN |
| Corrections Issued | 7/1/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 7/7/2021 | APPLICANT |
| Plan Check Approved | 7/13/2021 | PETER MOSESIAN |
| Issued | 7/20/2021 | APPLICANT |
| CofO in Progress | 11/3/2022 | MICHAEL LEWIS |
| Permit Finaled | 11/7/2022 | DEROLD HAUFF |
| CofO Issued | 11/7/2022 | DEROLD HAUFF |
| Permit Finaled | 11/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/1/2021 | JOHN BACON |
Contact Information
| Contractor | Agam Pool And Spa Inc; Lic. No.: 993464-C53 | 12940 ADDISON STREET SHERMAN OAKS, CA 91423 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 10/15/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Pre-Gunite | 11/1/2021 | Approved | ARTHUR SARGSYAN |
| Deputy Shotcrete | 11/2/2021 | Approved | ARTHUR SARGSYAN |
| Deck | 12/2/2021 | Approved | ARTHUR SARGSYAN |
| Grounding or Bonding | 12/2/2021 | Approved | ARTHUR SARGSYAN |
| Grounding or Bonding | 6/10/2022 | Approved | RYAN SALAZAR |
| Enclosure/Fence | 9/21/2022 | Approved | JOSEPH MCGARRY |
| Pool Equipment Noise Test | 10/6/2022 | Approved | ZEYDI STEWART |
| Excavation/Setback/Form/Re-Bar | 10/28/2022 | Approved | JEFFREY MEAD |
| Final | 10/28/2022 | Partial Approval | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 10/28/2022 | SGSOV Approved | JEFFREY MEAD |
| Final | 11/2/2022 | OK to Issue CofO | MICHAEL LEWIS |