14960 W SUTTON ST 91403
Certificate Information: 14960 W SUTTON ST 91403
- Application / Permit
- 21047-20000-01502
- Plan Check / Job No.
- B21VN08361
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 11'-0" x 35'-0" POOL AND 7'-0" x 7'-0" SPA PER CITY STD. PLAN #268 AND ENGINEERING DETAILS
- Permit Issued
- Issued on 7/12/2021
- Issuing Office
- Current Status
- CofO Issued on 3/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2021 | ALFRED RAMIREZ |
| Corrections Issued | 6/30/2021 | ALFRED RAMIREZ |
| Issued | 7/12/2021 | APPLICANT |
| Building Plans Picked Up | 7/13/2021 | APPLICANT |
| CofO in Progress | 12/10/2021 | JACK KARGODORIAN |
| Permit Finaled | 3/9/2022 | MICHAEL SMITH |
| CofO Issued | 3/9/2022 | MICHAEL SMITH |
| Permit Finaled | 3/9/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/30/2021 | ALFRED RAMIREZ |
Contact Information
| Contractor | Plascencia Pools & Landscaping; Lic. No.: 790546-C53 | 13803 LOUVRE STREET PACOIMA, CA 91331 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/23/2021 | Approved | CHARLES POWELL |
| Pool Piping | 8/23/2021 | Approved | CHARLES POWELL |
| Pre-Gunite | 8/23/2021 | Approved | CHARLES POWELL |
| Deputy Shotcrete | 8/24/2021 | Partial Approval | CHARLES POWELL |
| Gas Piping or Gas Test | 8/30/2021 | Approved | ALIZAH MAYAGOITIA |
| Deck | 9/24/2021 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 11/4/2021 | Approved | JACK KARGODORIAN |
| Pool Equipment Noise Test | 11/17/2021 | Approved | FELIPE PENICHE |
| Final | 11/19/2021 | Corrections Issued | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 11/19/2021 | SGSOV Approved | JACK KARGODORIAN |
| Final | 12/10/2021 | OK to Issue CofO | JACK KARGODORIAN |