4624 N BALBOA AVE 91316
Certificate Information: 4624 N BALBOA AVE 91316
- Application / Permit
- 21047-20000-01491
- Plan Check / Job No.
- B21VN08301
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW IRR. SHAPED 8' x 40'-7" POOL W/ 5'-8" x 7'-8" SPA; ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 1/24/2022
- Issuing Office
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | SEAN SHAHMIRI |
| Corrections Issued | 7/31/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 8/18/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/23/2021 | APPLICANT |
| Applicant returned to address corrections | 11/29/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 12/20/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 1/3/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 1/21/2022 | SEAN SHAHMIRI |
| Issued | 1/24/2022 | APPLICANT |
| CofO in Progress | 8/24/2022 | VINCENT HANLEY |
| CofO Issued | 8/27/2022 | MICHAEL SMITH |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 11/15/2021 | PABLO ESTRADA |
| Miscellaneous | Cleared | 11/15/2021 | PABLO ESTRADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jones,, Ryan Keith; Lic. No.: GE2852 | 1253 W MASLINE ST COVINA, CA 91722 |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/15/2022 | Approved | VINCENT HANLEY |
| Pre-Gunite | 2/15/2022 | Approved | VINCENT HANLEY |
| Rough-Electrical | 2/15/2022 | Approved | VINCENT HANLEY |
| Rough-Plumbing | 2/15/2022 | Approved | VINCENT HANLEY |
| Enclosure/Fence | 7/11/2022 | Corrections Issued | VINCENT HANLEY |
| Final | 7/11/2022 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Not Ready | VINCENT HANLEY |
| Final | 7/18/2022 | Partial Approval | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Approved | VINCENT HANLEY |
| Deck | 8/11/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 8/11/2022 | Approved | VINCENT HANLEY |
| Enclosure/Fence | 8/11/2022 | Approved | VINCENT HANLEY |
| Final | 8/11/2022 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 8/11/2022 | Approved | VINCENT HANLEY |
| Pool Equipment Noise Test | 8/11/2022 | Approved | ALFREDO FLORES |
| Pool/Spa Cover | 8/11/2022 | Approved | VINCENT HANLEY |
| Final | 8/24/2022 | OK to Issue CofO | VINCENT HANLEY |