23508 W SCHOENBORN ST 91304

Certificate Information: 23508 W SCHOENBORN ST 91304

Application / Permit
21047-20000-01481
Plan Check / Job No.
B21VN08235
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
REMODEL THE (E) POOL, REDUCE THE LENGTH BY 6' AND ADD 4'-8 7/8" TO THEOTHER SIDE BY HAVING A (N) 8'6" X 8'6" RAISED SPA, PER LA CITY STD. PLAN #268 AND DETAILS # 551 AND 640.
Permit Issued
Issued on 9/7/2021
Issuing Office
Valley
Current Status
CofO Issued on 11/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 PARISA ZAHABI
Corrections Issued 7/1/2021 PARISA ZAHABI
Applicant returned to address corrections 7/21/2021 PARISA ZAHABI
Building Plans Picked Up 7/22/2021 APPLICANT
Plan Check Approved 8/19/2021 PARISA ZAHABI
Issued 9/7/2021 APPLICANT
CofO in Progress 10/25/2022 CHRIS CHRISTENSEN
CofO Issued 11/4/2022 JOHN JANSON
Permit Finaled 11/4/2022 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/1/2021 PARISA ZAHABI
Construction near power lines Cleared 7/29/2021 WALTER RAMIREZ

Contact Information

Contractor Exclusive Pools Inc; Lic. No.: 343762-C53 18017 CHATSWORTH ST      GRANADA HILLS, CA 91344
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 9/24/2021 Approved DAVID STEPANYAN
Deck 10/29/2021 Approved DAVID STEPANYAN
Enclosure/Fence 11/17/2021 Corrections Issued DAVID STEPANYAN
Enclosure/Fence 12/15/2021 Approved VINCENT HANLEY
Pool Equipment Noise Test 1/25/2022 Approved ALFREDO FLORES
Excavation/Setback/Form/Re-Bar 10/17/2022 Approved CHRIS CHRISTENSEN
Final 10/17/2022 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/17/2022 SGSOV Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 10/24/2022 Approved CHRIS CHRISTENSEN
Final 10/24/2022 OK to Issue CofO CHRIS CHRISTENSEN
Special/Order Compliance 11/1/2022 Approved CHRIS CHRISTENSEN