521 N FORMOSA AVE 90036

Certificate Information: 521 N FORMOSA AVE 90036

Application / Permit
21047-20000-01471
Plan Check / Job No.
B21VN08192
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 29' X 13 'POOL WITH A 7' X 9' SPA PER LA CITY STANDARD PLAN #270
Permit Issued
Issued on 9/17/2021
Issuing Office
Current Status
CofO Issued on 4/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2021 APPLICANT
Assigned to Plan Check Engineer 6/25/2021 OMAR GARNICA
Corrections Issued 6/25/2021 OMAR GARNICA
Applicant returned to address corrections 7/15/2021 OMAR GARNICA
Applicant returned to address corrections 8/24/2021 OMAR GARNICA
Plan Check Approved 9/17/2021 OMAR GARNICA
Issued 9/17/2021 APPLICANT
Building Plans Picked Up 9/17/2021 APPLICANT
CofO in Progress 3/9/2022 CHRIS CHRISTENSEN
Permit Finaled 4/1/2022 DEROLD HAUFF
CofO Issued 4/1/2022 DEROLD HAUFF
Permit Finaled 4/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 7/27/2021 WALTER RAMIREZ

Contact Information

Contractor L E Construction & Development Inc; Lic. No.: 1051866-B 7111 SANTA MONICA BLVD   SUITE B-272    LOS ANGELES, CA 90046
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Shotcrete 9/20/2021 Conditional Approval CHRIS CHRISTENSEN
Pool Piping 9/20/2021 Approved CHRIS CHRISTENSEN
Pre-Gunite 9/20/2021 Approved CHRIS CHRISTENSEN
Deck 10/4/2021 Approved CHRIS CHRISTENSEN
Special/Order Compliance 11/19/2021 Corrections Issued AMY COLIN
Excavation/Setback/Form/Re-Bar 11/24/2021 Approved CHRIS CHRISTENSEN
Final 11/24/2021 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/24/2021 SGSOV Not Ready CHRIS CHRISTENSEN
Final 12/13/2021 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 12/13/2021 SGSOV Approved CHRIS CHRISTENSEN
Final 12/20/2021 Corrections Issued CRAIG DAVIS
Final 12/28/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Final 1/10/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 1/13/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 1/21/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Special/Order Compliance 2/1/2022 Partial Approval CHRIS CHRISTENSEN
Pool Equipment Noise Test 2/15/2022 No Access for Inspection JUSTIN CURTIS
Final 2/24/2022 Corrections Issued CHRIS CHRISTENSEN
Final 3/3/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 3/8/2022 OK to Issue CofO CHRIS CHRISTENSEN
Pool Equipment Noise Test 3/8/2022 Approved JUSTIN CURTIS