9520 W KIRKSIDE ROAD 90035
Certificate Information: 9520 W KIRKSIDE ROAD 90035
- Application / Permit
- 21047-20000-01469
- Plan Check / Job No.
- B21VN08169
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW 12'X22' SWIMMING POOL W/ 5'X6' SPA PER CITY STD PLAN # 268. SEE COMMENTS
- Permit Issued
- Issued on 7/19/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 6/25/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 7/9/2021 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 7/13/2021 | APPLICANT |
| Issued | 7/19/2021 | APPLICANT |
| CofO in Progress | 8/15/2022 | OGANES TARAKHCHYAN |
| CofO Issued | 8/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Agam Pool And Spa Inc; Lic. No.: 993464-C53 | 12940 ADDISON STREET SHERMAN OAKS, CA 91423 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 11/10/2021 | Corrections Issued | KEVIN SARGSYAN |
| Gunite | 11/15/2021 | Conditional Approval | KEVIN SARGSYAN |
| Deck | 12/6/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Enclosure/Fence | 12/6/2021 | Corrections Issued | KEVIN SARGSYAN |
| Grounding or Bonding | 12/6/2021 | Corrections Issued | KEVIN SARGSYAN |
| Enclosure/Fence | 2/11/2022 | Approved | KEVIN SARGSYAN |
| Pool Equipment Noise Test | 2/25/2022 | Approved | ROBERT CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 7/15/2022 | Approved | KEVIN SARGSYAN |
| Final | 7/15/2022 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Gunite | 7/15/2022 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 8/8/2022 | Partial Approval | OGANES TARAKHCHYAN |