11086 W SUNSET BLVD 90049

Certificate Information: 11086 W SUNSET BLVD 90049

Application / Permit
21047-20000-01468
Plan Check / Job No.
B21VN08164
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW (42'-6"x10'-0") POOL AND (6'-0"x7'-0") SPA AND BAJA PER STANDARD PLAN #268
Permit Issued
Issued on 9/16/2021
Issuing Office
Current Status
CofO Issued on 10/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2021 APPLICANT
Assigned to Plan Check Engineer 6/28/2021 PETER MOSESIAN
Corrections Issued 6/29/2021 PETER MOSESIAN
Building Plans Picked Up 7/6/2021 APPLICANT
Applicant returned to address corrections 8/18/2021 PETER MOSESIAN
Plan Check Approved 8/19/2021 PETER MOSESIAN
Issued 9/16/2021 APPLICANT
CofO in Progress 9/17/2022 CARLOS MATAMOROS
Permit Finaled 10/28/2022 DANIEL ORRANTE
CofO Issued 10/28/2022 DANIEL ORRANTE
Permit Finaled 10/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 7/29/2021 MIGUEL GAMBOA

Contact Information

Contractor Maxim Pool And Spa Construction; Lic. No.: 839597-C53 23321 GILMORE ST      WEST HILLS, CA 91307

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/21/2021 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/12/2021 Not Ready for Inspection CARLOS MATAMOROS
Grounding or Bonding 10/14/2021 Approved CARLOS MATAMOROS
Pre-Gunite 10/14/2021 Approved CARLOS MATAMOROS
Deputy Other (see comments) 11/17/2021 Conditional Approval DEANDRE HOFFMAN
Deputy Shotcrete 11/17/2021 Conditional Approval DEANDRE HOFFMAN
Pool Piping 11/23/2021 Partial Approval BRENDAN LOONEY
Deck 12/29/2021 Approved GERMAN RODRIGUEZ MENDOZA
Grounding or Bonding 12/29/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Pool Piping 12/29/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Enclosure/Fence 2/18/2022 Corrections Issued KRISTEN CAUSEY
Pool Piping 2/18/2022 Not Ready for Inspection KRISTEN CAUSEY
Enclosure/Fence 3/1/2022 Not Ready for Inspection CHRISTOPHER WILSON
Enclosure/Fence 4/1/2022 Approved GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 4/15/2022 Approved CARLOS MATAMOROS
Final 4/15/2022 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 4/15/2022 SGSOV Not Ready CARLOS MATAMOROS
Pool Equipment Noise Test 6/3/2022 Approved ROBERT CHAVEZ
Final 6/15/2022 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 6/15/2022 SGSOV Not Ready CARLOS MATAMOROS
Final 9/16/2022 OK to Issue CofO CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved CARLOS MATAMOROS