17943 W MALDEN ST 91325
Certificate Information: 17943 W MALDEN ST 91325
- Application / Permit
- 21047-20000-01385
- Plan Check / Job No.
- B21VN07613
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 20' X 40' POOL AND 7' X 8' SPA PER LA CITY STANDARD PLAN #268
- Permit Issued
- Issued on 10/20/2021
- Issuing Office
- Current Status
- CofO Issued on 3/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2021 | OMAR GARNICA |
| Corrections Issued | 6/17/2021 | OMAR GARNICA |
| Applicant returned to address corrections | 10/5/2021 | OMAR GARNICA |
| Plan Check Approved | 10/20/2021 | OMAR GARNICA |
| Issued | 10/20/2021 | APPLICANT |
| Building Plans Picked Up | 10/21/2021 | APPLICANT |
| CofO in Progress | 5/19/2022 | JAVIER RAMOS JR |
| CofO in Progress | 5/19/2022 | JAVIER RAMOS JR |
| CofO in Progress | 3/8/2023 | JAVIER RAMOS JR |
| Permit Finaled | 3/29/2023 | MICHAEL SMITH |
| CofO Issued | 3/29/2023 | MICHAEL SMITH |
| Permit Finaled | 3/29/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 8/18/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2021 | CARLOS AGUILERA |
| Metro Rail approval | Cleared | 9/13/2021 | OMAR GARNICA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/12/2021 | Partial Inspection | MARK JOHNSON |
| Gas Piping or Gas Test | 12/13/2021 | Approved | MARK JOHNSON |
| Pool Piping | 12/13/2021 | Approved | MARK JOHNSON |
| Pre-Gunite | 12/13/2021 | Approved | MARK JOHNSON |
| Rough-Electrical | 12/13/2021 | Approved | MARK JOHNSON |
| Rough-Plumbing | 12/13/2021 | Approved | MARK JOHNSON |
| Grounding or Bonding | 1/27/2022 | Approved | MICHAEL TEMPLE |
| Deputy Shotcrete | 2/17/2022 | Approved | RAUL OLAGI |
| Enclosure/Fence | 2/17/2022 | Corrections Issued | RAUL OLAGI |
| Enclosure/Fence | 2/23/2022 | Corrections Issued | RAUL OLAGI |
| Enclosure/Fence | 3/21/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 3/30/2022 | Approved | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 3/30/2022 | Approved | ROBERT GOLD |
| Final | 3/30/2022 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Final | 3/30/2022 | Approved | ROBERT GOLD |
| Pool Equipment Noise Test | 3/30/2022 | Approved | ALFREDO FLORES |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Approved | ROBERT GOLD |
| Final | 5/13/2022 | Partial Approval | JAVIER RAMOS JR |
| Final | 5/19/2022 | OK to Issue CofO | JAVIER RAMOS JR |
| Special/Order Compliance | 5/23/2022 | Corrections Issued | JAVIER RAMOS JR |
| Final | 5/26/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 3/8/2023 | OK to Issue CofO | JAVIER RAMOS JR |