17911 W TOPHAM ST 91316
Certificate Information: 17911 W TOPHAM ST 91316
- Application / Permit
- 21047-20000-01358
- Plan Check / Job No.
- B21VN07522
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 20 X 32 POOL WITH A 15' X 8' SPA AND BAJA PER LA CITY STANDARD PLAN # 268.
- Permit Issued
- Issued on 12/16/2021
- Issuing Office
- Current Status
- CofO Issued on 8/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2021 | PARISA ZAHABI |
| Corrections Issued | 6/15/2021 | PARISA ZAHABI |
| Plan Check Approved | 12/13/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 12/13/2021 | APPLICANT |
| Issued | 12/16/2021 | APPLICANT |
| CofO in Progress | 6/29/2022 | SEAN HAUPT |
| Permit Finaled | 8/16/2022 | JOHN JANSON |
| CofO Issued | 8/16/2022 | JOHN JANSON |
| Permit Finaled | 8/16/2022 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/22/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Home Sweet Home Remodeling Inc; Lic. No.: 1073895-B | 17911 TOPHAM STREET ENCINO, CA 91316 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/3/2022 | Approved | SEAN HAUPT |
| Grounding or Bonding | 1/3/2022 | Approved | SEAN HAUPT |
| Rough-Electrical | 1/3/2022 | Approved | SEAN HAUPT |
| Rough-Plumbing | 1/3/2022 | Approved | SEAN HAUPT |
| Deputy Shotcrete | 1/5/2022 | Approved | SEAN HAUPT |
| Grounding or Bonding | 1/31/2022 | Approved | RYAN SALAZAR |
| Enclosure/Fence | 3/1/2022 | Approved | SEAN HAUPT |
| Equipment Noise Level | 3/21/2022 | Approved | FELIPE PENICHE |
| Final | 3/21/2022 | Corrections Issued | SEAN HAUPT |
| Pre-Gunite | 3/21/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Approved | SEAN HAUPT |
| Final | 6/28/2022 | OK to Issue CofO | SEAN HAUPT |