827 S GENESEE AVE 90036
Certificate Information: 827 S GENESEE AVE 90036
- Application / Permit
- 21047-20000-01348
- Plan Check / Job No.
- B21VN07453
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW IRREGULAR 15' x 30'8" POOL WITH A 8' x 8' SPA WITH ASTM F-1346 POOL COVER.
- Permit Issued
- Issued on 9/8/2021
- Issuing Office
- Current Status
- CofO Corrected on 12/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2021 | LUIS RINCON |
| Corrections Issued | 6/16/2021 | LUIS RINCON |
| Applicant returned to address corrections | 8/20/2021 | LUIS RINCON |
| Plan Check Approved | 9/7/2021 | LUIS RINCON |
| Issued | 9/8/2021 | APPLICANT |
| Building Plans Picked Up | 9/10/2021 | APPLICANT |
| CofO in Progress | 11/9/2022 | MICHAEL LEWIS |
| CofO Issued-Status Void | 12/10/2022 | DEROLD HAUFF |
| Permit Finaled-Status Void | 12/10/2022 | DEROLD HAUFF |
| Re-Activate Permit | 12/6/2023 | DEROLD HAUFF |
| Permit Finaled | 12/7/2023 | DEROLD HAUFF |
| CofO Corrected | 12/7/2023 | DEROLD HAUFF |
| Permit Finaled | 12/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 9/7/2021 | LUIS RINCON |
Contact Information
| Contractor | Premier Pool Plastering; Lic. No.: 625132-C53 | 14520 FOOTHILL BLVD SYLMAR, CA 91342 |
| Engineer | Rosas,, Alejandro; Lic. No.: C67650 | 953 CRONE COURT SANTA ROSA, CA 95407 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 10/26/2021 | Approved | ARTHUR SARGSYAN |
| Deck | 12/16/2021 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 4/15/2022 | No Access for Inspection | JUSTIN CURTIS |
| Final | 4/15/2022 | No Access for Inspection | JUSTIN CURTIS |
| SGSOV-Seismic Gas S/O Valve | 4/15/2022 | SGSOV Not Ready | JUSTIN CURTIS |
| Excavation/Setback/Form/Re-Bar | 4/25/2022 | Approved | ARTHUR SARGSYAN |
| Final | 4/25/2022 | Corrections Issued | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Approved | ARTHUR SARGSYAN |
| Final | 10/20/2022 | Corrections Issued | MICHAEL LEWIS |
| Final | 11/9/2022 | OK to Issue CofO | MICHAEL LEWIS |