7113 N LASAINE AVE 91406
Certificate Information: 7113 N LASAINE AVE 91406
- Application / Permit
- 21047-20000-01324
- Plan Check / Job No.
- B21VN07311
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 27' X 17' POOL WITH A 7' X 7' SPA PER LA CITY STANDARD PLAN #268
- Permit Issued
- Issued on 11/5/2021
- Issuing Office
- Current Status
- CofO Issued on 4/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2021 | JESSE ARELLANO |
| Corrections Issued | 6/11/2021 | JESSE ARELLANO |
| Issued | 11/5/2021 | APPLICANT |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| CofO in Progress | 4/6/2022 | SEAN HAUPT |
| CofO Issued | 4/7/2022 | MICHAEL SMITH |
| Permit Finaled | 4/7/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/23/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/11/2022 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 1/18/2022 | Corrections Issued | SEAN HAUPT |
| Gas Piping or Gas Test | 1/18/2022 | Approved | SEAN HAUPT |
| Pre-Gunite | 1/18/2022 | Not Ready for Inspection | SEAN HAUPT |
| Rough-Electrical | 1/18/2022 | Approved | SEAN HAUPT |
| Rough-Plumbing | 1/18/2022 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 1/27/2022 | Approved | SEAN WIRCH |
| Pre-Gunite | 1/27/2022 | Approved | SEAN WIRCH |
| Deputy Shotcrete | 1/31/2022 | Conditional Approval | RYAN SALAZAR |
| Grounding or Bonding | 2/11/2022 | Approved | SEAN HAUPT |
| Enclosure/Fence | 2/28/2022 | Approved | SEAN HAUPT |
| Pool Equipment Noise Test | 3/18/2022 | Approved | ALFREDO FLORES |
| Final | 3/30/2022 | Corrections Issued | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Approved | SEAN HAUPT |
| Final | 4/5/2022 | OK to Issue CofO | SEAN HAUPT |