4943 N WOODMAN AVE 91423
Certificate Information: 4943 N WOODMAN AVE 91423
- Application / Permit
- 21047-20000-01304
- Plan Check / Job No.
- B21VN07152
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 32' X 14' POOL WITH 8' X 8' SPA PER STANDARD PLAN 268.
- Permit Issued
- Issued on 7/19/2021
- Issuing Office
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2021 | SERGIO MUNIZ |
| Corrections Issued | 6/9/2021 | SERGIO MUNIZ |
| Plan Check Approved | 7/19/2021 | SERGIO MUNIZ |
| Issued | 7/19/2021 | APPLICANT |
| Building Plans Picked Up | 7/27/2021 | APPLICANT |
| CofO in Progress | 1/5/2022 | JENNIFER RABUCHIN |
| Permit Finaled | 1/22/2022 | MICHAEL SMITH |
| CofO Issued | 1/22/2022 | MICHAEL SMITH |
| Permit Finaled | 1/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/19/2021 | JOHN BACON |
Contact Information
| Contractor | Intex Design And Construction Inc; Lic. No.: 981718-C53 | 2646 DUPONT DR STE 60 #348 IRVINE, CA 92612 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/17/2021 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 9/17/2021 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 9/17/2021 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 9/17/2021 | Approved | ARAM AVEDISIAN |
| Rough-Plumbing | 9/17/2021 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 9/17/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Grounding or Bonding | 10/14/2021 | Approved | MISAEL ESPARZA |
| Deck | 11/8/2021 | Approved | MISAEL ESPARZA |
| Grounding or Bonding | 11/8/2021 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 11/23/2021 | Approved | MISAEL ESPARZA |
| Equipment Noise Level | 12/6/2021 | Approved | ALFREDO FLORES |
| Pool Equipment Noise Test | 12/6/2021 | Approved | ALFREDO FLORES |
| Final | 12/14/2021 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/14/2021 | SGSOV Not Ready | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/4/2022 | Approved | JENNIFER RABUCHIN |
| Final | 1/4/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/4/2022 | SGSOV Approved | JENNIFER RABUCHIN |