4943 N WOODMAN AVE 91423

Certificate Information: 4943 N WOODMAN AVE 91423

Application / Permit
21047-20000-01304
Plan Check / Job No.
B21VN07152
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 32' X 14' POOL WITH 8' X 8' SPA PER STANDARD PLAN 268.
Permit Issued
Issued on 7/19/2021
Issuing Office
Current Status
CofO Issued on 1/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2021 APPLICANT
Assigned to Plan Check Engineer 6/9/2021 SERGIO MUNIZ
Corrections Issued 6/9/2021 SERGIO MUNIZ
Plan Check Approved 7/19/2021 SERGIO MUNIZ
Issued 7/19/2021 APPLICANT
Building Plans Picked Up 7/27/2021 APPLICANT
CofO in Progress 1/5/2022 JENNIFER RABUCHIN
Permit Finaled 1/22/2022 MICHAEL SMITH
CofO Issued 1/22/2022 MICHAEL SMITH
Permit Finaled 1/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 7/19/2021 JOHN BACON

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-C53 2646 DUPONT DR STE 60 #348      IRVINE, CA 92612
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/17/2021 Approved ARAM AVEDISIAN
Grounding or Bonding 9/17/2021 Partial Approval ARAM AVEDISIAN
Pool Piping 9/17/2021 Approved ARAM AVEDISIAN
Pre-Gunite 9/17/2021 Approved ARAM AVEDISIAN
Rough-Plumbing 9/17/2021 Approved ARAM AVEDISIAN
Special/Order Compliance 9/17/2021 Partial Inspection ALIZAH MAYAGOITIA
Grounding or Bonding 10/14/2021 Approved MISAEL ESPARZA
Deck 11/8/2021 Approved MISAEL ESPARZA
Grounding or Bonding 11/8/2021 Approved MISAEL ESPARZA
Enclosure/Fence 11/23/2021 Approved MISAEL ESPARZA
Equipment Noise Level 12/6/2021 Approved ALFREDO FLORES
Pool Equipment Noise Test 12/6/2021 Approved ALFREDO FLORES
Final 12/14/2021 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 12/14/2021 SGSOV Not Ready MISAEL ESPARZA
ELECTRICAL-Final 1/4/2022 Approved JENNIFER RABUCHIN
Final 1/4/2022 OK to Issue CofO JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/4/2022 SGSOV Approved JENNIFER RABUCHIN