14944 W HESBY ST 91403

Certificate Information: 14944 W HESBY ST 91403

Application / Permit
21047-20000-01228
Plan Check / Job No.
B21VN06634
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED NEW 13'X34' SWIMMING POOL W/ SPA PER CITY STD PLAN #268 & 6' HIGH WALL ABOVE BOND BEAM PER ENGR DETAIL. SEE COMMENTS.
Permit Issued
Issued on 7/30/2021
Issuing Office
Current Status
CofO Issued on 7/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2021 APPLICANT
Assigned to Plan Check Engineer 5/27/2021 HAYATO TSUCHIYA
Corrections Issued 5/27/2021 HAYATO TSUCHIYA
Plan Check Approved 5/27/2021 HAYATO TSUCHIYA
No Progress 5/27/2021 HAYATO TSUCHIYA
Plan Check Approved 7/28/2021 HAYATO TSUCHIYA
Building Plans Picked Up 7/28/2021 APPLICANT
Issued 7/30/2021 APPLICANT
CofO in Progress 11/3/2021 JACK KARGODORIAN
CofO Issued 7/16/2022 MICHAEL SMITH
Permit Finaled 7/16/2022 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Athlon Pool Company Inc; Lic. No.: 970093-C53 150 S GLENOAKS BLVD #9152      BURBANK, CA 91502
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 8/17/2021 Partial Approval THOMAS FINNILA
Pre-Gunite 8/17/2021 Approved THOMAS FINNILA
Deck 9/3/2021 Approved CHARLES POWELL
Gas Piping or Gas Test 9/3/2021 Approved CHARLES POWELL
Grounding or Bonding 9/3/2021 Approved CHARLES POWELL
Pool Piping 9/3/2021 Approved CHARLES POWELL
Rough-Electrical 9/3/2021 Approved CHARLES POWELL
Rough-Plumbing 9/3/2021 Approved CHARLES POWELL
Enclosure/Fence 9/13/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 10/4/2021 Approved MICHAEL PELHAM
Final 10/4/2021 Corrections Issued MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 10/4/2021 SGSOV Not Ready MICHAEL PELHAM
Final 10/5/2021 Not Ready for Inspection MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 10/5/2021 SGSOV Not Ready MICHAEL PELHAM
Final 10/13/2021 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/13/2021 SGSOV Not Ready JACK KARGODORIAN
Final 10/21/2021 OK to Issue CofO JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/21/2021 SGSOV Approved JACK KARGODORIAN