20837 W ACORN CIR 91326

Certificate Information: 20837 W ACORN CIR 91326

Application / Permit
21047-20000-01166
Plan Check / Job No.
B21VN06348
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL (15'-0" X 30'-0") W/ COVER AND BAJA PER STANDARD PLAN #268
Permit Issued
Issued on 7/22/2021
Issuing Office
Current Status
CofO Issued on 12/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2021 APPLICANT
Assigned to Plan Check Engineer 5/21/2021 PETER MOSESIAN
Corrections Issued 5/22/2021 PETER MOSESIAN
Applicant returned to address corrections 6/9/2021 LUISANGEL VALENZUELA
Building Plans Picked Up 6/10/2021 APPLICANT
Applicant returned to address corrections 6/27/2021 PETER MOSESIAN
Plan Check Approved 7/9/2021 PETER MOSESIAN
Issued 7/22/2021 APPLICANT
CofO in Progress 12/10/2021 DAVID SCANTLIN
Permit Finaled 12/14/2021 JOHN JANSON
CofO Issued 12/14/2021 JOHN JANSON
Permit Finaled 12/14/2021 JOHN JANSON

Permit Application Clearance Information

ZA Case Cleared 7/7/2021 DANG NGUYEN
ZA Case Cleared 7/7/2021 DANG NGUYEN
ZA Case Cleared 7/7/2021 DANG NGUYEN
ZA Case Cleared 7/7/2021 DANG NGUYEN
ZA Case Cleared 7/7/2021 DANG NGUYEN
ZA Case Cleared 7/7/2021 DANG NGUYEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deck 9/15/2021 Corrections Issued DAVID SANDOVAL
Pre-Gunite 9/15/2021 Approved DAVID SANDOVAL
Deputy Shotcrete 9/24/2021 Conditional Approval KRISTEN CAUSEY
Deck 10/6/2021 Approved DAVID SCANTLIN
Enclosure/Fence 10/29/2021 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 11/9/2021 Approved DAVID SCANTLIN
Final 11/9/2021 Corrections Issued DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/9/2021 SGSOV Approved DAVID SCANTLIN
Pool Equipment Noise Test 11/15/2021 Not Ready for Inspection FELIPE PENICHE
Equipment Noise Level 11/16/2021 Approved ALFREDO FLORES
Final 12/3/2021 OK to Issue CofO DAVID SCANTLIN