5807 N VESPER AVE 91411
Certificate Information: 5807 N VESPER AVE 91411
- Application / Permit
- 21047-20000-01150
- Plan Check / Job No.
- B21VN06270
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14'-0" x 18'-0" POOL AND 6'-0" x 7'-0" SPA PER CITY STANDARD PLAN #265
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- CofO Issued on 7/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | ALFRED RAMIREZ |
| Corrections Issued | 5/20/2021 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 1/3/2022 | ALFRED RAMIREZ |
| Plan Check Approved | 2/3/2022 | ALFRED RAMIREZ |
| Plan Check Approved | 2/14/2022 | ALFRED RAMIREZ |
| Issued | 2/23/2022 | APPLICANT |
| Building Plans Picked Up | 3/1/2022 | APPLICANT |
| CofO in Progress | 6/26/2023 | RYAN SALAZAR |
| CofO Issued | 7/14/2023 | JOHN JANSON |
| Permit Finaled | 7/14/2023 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/24/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/10/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Pre-Gunite | 8/15/2022 | Corrections Issued | RICHARD DOCKUS |
| Grounding or Bonding | 8/29/2022 | Corrections Issued | RICHARD DOCKUS |
| Pre-Gunite | 8/29/2022 | Approved | RICHARD DOCKUS |
| Grounding or Bonding | 9/2/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 9/8/2022 | Approved | RICHARD DOCKUS |
| Grounding or Bonding | 9/8/2022 | Approved | RICHARD DOCKUS |
| Enclosure/Fence | 4/19/2023 | Corrections Issued | RYAN SALAZAR |
| Gas Piping or Gas Test | 4/19/2023 | Approved | RYAN SALAZAR |
| Rough-Electrical | 4/19/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Not Ready | RYAN SALAZAR |
| Enclosure/Fence | 5/2/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/2/2023 | SGSOV Approved | RYAN SALAZAR |
| Final | 6/23/2023 | OK to Issue CofO | RYAN SALAZAR |
| Pool Equipment Noise Test | 6/23/2023 | Approved | ALFREDO FLORES |