4876 N WICOPEE AVE 90041
Certificate Information: 4876 N WICOPEE AVE 90041
- Application / Permit
- 21047-20000-01148
- Plan Check / Job No.
- B21VN06252
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 32'-0" x 14'-0" POOL PER CITY STANDARD PLAN #268 AND ENGINEERING DETAILS
- Permit Issued
- Issued on 5/27/2021
- Issuing Office
- Current Status
- CofO Issued on 9/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2021 | ALFRED RAMIREZ |
| Corrections Issued | 5/24/2021 | ALFRED RAMIREZ |
| Issued | 5/27/2021 | APPLICANT |
| Building Plans Picked Up | 5/27/2021 | APPLICANT |
| CofO in Progress | 8/17/2022 | CRAIG VAUGHAN |
| CofO in Progress | 8/17/2022 | CRAIG VAUGHAN |
| Permit Finaled | 9/8/2022 | DEROLD HAUFF |
| CofO Issued | 9/8/2022 | DEROLD HAUFF |
| Permit Finaled | 9/8/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/24/2021 | ALFRED RAMIREZ |
Contact Information
| Contractor | Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 | 978 NORTH AMEILA AVE SAN DIMAS, CA 91773 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 10/15/2021 | Approved | CRAIG VAUGHAN |
| Deck | 5/26/2022 | Corrections Issued | CRAIG VAUGHAN |
| Enclosure/Fence | 5/26/2022 | Corrections Issued | CRAIG VAUGHAN |
| Deck | 7/6/2022 | Approved | RUBEN SALAS |
| Enclosure/Fence | 7/6/2022 | Approved | RUBEN SALAS |
| Grounding or Bonding | 8/4/2022 | Approved | HAMIK HARTOUNIAN |
| Pool Equipment Noise Test | 8/4/2022 | Approved | ROBERT CHAVEZ |
| ELECTRICAL-Final | 8/16/2022 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/16/2022 | Approved | CRAIG VAUGHAN |
| Final | 8/16/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| PLUMBING-Final | 8/16/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/16/2022 | SGSOV Approved | CRAIG VAUGHAN |