18019 W GAUGUIN LANE 91344
Certificate Information: 18019 W GAUGUIN LANE 91344
- Application / Permit
- 21047-20000-01146
- Plan Check / Job No.
- B21VN06248
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 17' X 32' SWIMMING POOL AND 7' X 7' SPA WITHIN PER STANDARD PLAN #268 AND ENGINEER DETAIL
- Permit Issued
- Issued on 8/24/2021
- Issuing Office
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 5/20/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 7/7/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 8/13/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/18/2021 | APPLICANT |
| Issued | 8/24/2021 | APPLICANT |
| CofO in Progress | 8/2/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/4/2025 | MICHAEL PELHAM |
| CofO Issued | 9/4/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/4/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/26/2021 | LAUREN PADICK |
| Miscellaneous | Cleared | 5/26/2021 | LAUREN PADICK |
| Tract Map conditions | Cleared | 5/26/2021 | LAUREN PADICK |
| Grading Pre-Inspection | Cleared | 8/13/2021 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Way To Go Builders; Lic. No.: 1043721-B | 6700 FALLBROOK AVE STE 133 WEST HILLS, CA 91307 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/28/2021 | Approved | DAVID SCANTLIN |
| Pre-Gunite | 3/7/2022 | Approved | DAVID SCANTLIN |
| Deputy Other (see comments) | 3/10/2022 | Conditional Approval | JUSTIN HAWLEY |
| Deputy Shotcrete | 3/10/2022 | Conditional Approval | JUSTIN HAWLEY |
| Grounding or Bonding | 4/7/2022 | Approved | DAVID SCANTLIN |
| Enclosure/Fence | 5/10/2022 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 5/19/2022 | Approved | DAVID SCANTLIN |
| Final | 5/19/2022 | Corrections Issued | DAVID SCANTLIN |
| Grading Pre-Inspection | 5/19/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Pool Equipment Noise Test | 5/19/2022 | Approved | ALFREDO FLORES |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Not Ready | DAVID SCANTLIN |
| Equipment Noise Level | 5/24/2022 | Approved | FELIPE PENICHE |
| Final | 5/24/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Approved | DAVID SCANTLIN |
| Final | 8/2/2025 | OK to Issue CofO | MICHAEL PELHAM |