11549 W ADDISON ST 91601
Certificate Information: 11549 W ADDISON ST 91601
- Application / Permit
- 21047-20000-01142
- Plan Check / Job No.
- B21VN06226
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16 X 21.6 POOL WITH A 6 X 16 SPA PER STANDARD PLAN 270
- Permit Issued
- Issued on 6/4/2021
- Issuing Office
- Current Status
- CofO Issued on 10/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2021 | ALYSSA N NARCISO |
| Corrections Issued | 5/24/2021 | ALYSSA N NARCISO |
| Plan Check Approved | 6/4/2021 | ALYSSA N NARCISO |
| Issued | 6/4/2021 | APPLICANT |
| Building Plans Picked Up | 6/7/2021 | APPLICANT |
| CofO in Progress | 10/8/2021 | CHRISTOPHE COCHRAN |
| Permit Finaled | 10/15/2021 | MICHAEL SMITH |
| CofO Issued | 10/15/2021 | MICHAEL SMITH |
| Permit Finaled | 10/15/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 6/1/2021 | MIGUEL GAMBOA |
| Specific Plan | Cleared | 6/1/2021 | MIGUEL GAMBOA |
Contact Information
| Contractor | Pepe'S Pools Inc; Lic. No.: 1028041-C53 | 4817 YORK BLVD LOS ANGELES, CA 90042 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/28/2021 | Conditional Approval | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/23/2021 | SGSOV Not Ready | THOMAS FINNILA |
| Gas Piping or Gas Test | 7/27/2021 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 8/12/2021 | Partial Approval | THOMAS FINNILA |
| Enclosure/Fence | 9/7/2021 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 9/9/2021 | Approved | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 10/6/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 10/6/2021 | Conditional Approval | CHRISTOPHE COCHRAN |
| Pre-Gunite | 10/6/2021 | Approved | CHRISTOPHE COCHRAN |
| Rough-Electrical | 10/6/2021 | Approved | CHRISTOPHE COCHRAN |
| Rough-Plumbing | 10/6/2021 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 10/6/2021 | SGSOV Approved | CHRISTOPHE COCHRAN |