4818 W BONVUE AVE 90027
Certificate Information: 4818 W BONVUE AVE 90027
- Application / Permit
- 21047-20000-01137
- Plan Check / Job No.
- B21VN06206
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW (40'-0"x 14'-0") STRUCTURAL POOL WITH GARADE BEAM AND PILES. WORK PER ENGINEER.
- Permit Issued
- Issued on 7/30/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | ALYSSA N NARCISO |
| Corrections Issued | 6/30/2021 | ALYSSA N NARCISO |
| Quality Review Completed | 7/2/2021 | STEVEN KIM |
| Building Plans Picked Up | 8/12/2021 | APPLICANT |
| Applicant returned to address corrections | 8/4/2022 | TROY DEGUZMAN |
| Plan Check Approved | 9/29/2022 | SELLA BENYAMIN |
| Issued | 7/30/2024 | APPLICANT |
| CofO in Progress | 10/16/2025 | ENRIQUE MIRELES |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
| CofO Issued | 10/17/2025 | DEROLD HAUFF |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 8/4/2022 | ROBERT HUGHES |
| Grading Pre-Inspection | Cleared | 8/4/2022 | ROBERT HUGHES |
Contact Information
| Contractor | Addison Pools Inc; Lic. No.: 753417-C53 | 4363 WOODMAN AVENUE SHERMAN OAKS, CA 91423 |
| Engineer | Polon,, Gordon Leonard; Lic. No.: C28564 | 709 19TH STREET SANTA MONICA, CA 90402 |
| Geologist | Cugno,, Giuseppe; Lic. No.: EG1804 | 1461 E CHEVY CHASE DR 200 BYER GEOTECHNICAL, INC. GLENDALE, CA 91206 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/15/2024 | Approved | ENRIQUE MIRELES |
| Piling/Pier/Caisson | 11/1/2024 | Approved | ENRIQUE MIRELES |
| Deputy Shotcrete | 11/8/2024 | Approved | ENRIQUE MIRELES |
| Deputy Shotcrete | 11/12/2024 | Approved | ENRIQUE MIRELES |
| Piling/Pier/Caisson | 12/3/2024 | Approved | ENRIQUE MIRELES |
| Deputy Other (see comments) | 12/6/2024 | Approved | ENRIQUE MIRELES |
| Pre-Gunite | 3/7/2025 | Approved | ENRIQUE MIRELES |
| Rough-Electrical | 3/7/2025 | Approved | ENRIQUE MIRELES |
| Rough-Plumbing | 3/7/2025 | Approved | ENRIQUE MIRELES |
| Deputy Shotcrete | 3/14/2025 | Approved | ENRIQUE MIRELES |
| Deputy Shotcrete | 3/17/2025 | Approved | ENRIQUE MIRELES |
| Gas Piping or Gas Test | 7/22/2025 | Approved | BRENDAN MORELLI |
| Rough-Electrical | 7/22/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Rough-Electrical | 7/28/2025 | Corrections Issued | BRENDAN MORELLI |
| Deck | 8/29/2025 | Approved | ENRIQUE MIRELES |
| Enclosure/Fence | 8/29/2025 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/22/2025 | Approved | ENRIQUE MIRELES |
| Final | 9/22/2025 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/22/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Final | 10/7/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 10/14/2025 | OK to Issue CofO | ENRIQUE MIRELES |