13274 W PARKLAND CIR 91342
Certificate Information: 13274 W PARKLAND CIR 91342
- Application / Permit
- 21047-20000-01136
- Plan Check / Job No.
- B21VN06205
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW (53'-0"x 28'-7") POOL WITH A LAZY RIVER/BAJA AND 8' DIAMETER SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 7/12/2021
- Issuing Office
- Current Status
- CofO Issued on 4/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2021 | PETER MOSESIAN |
| Corrections Issued | 5/21/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 5/25/2021 | APPLICANT |
| Issued | 7/12/2021 | APPLICANT |
| CofO in Progress | 3/17/2023 | ARAM AVEDISIAN |
| No Progress | 3/21/2023 | ARAM AVEDISIAN |
| CofO in Progress | 3/24/2023 | ARAM AVEDISIAN |
| Permit Finaled | 4/14/2023 | MICHAEL SMITH |
| CofO Issued | 4/14/2023 | MICHAEL SMITH |
| Permit Finaled | 4/14/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Premier Pool Plastering; Lic. No.: 625132-C53 | 14520 FOOTHILL BLVD SYLMAR, CA 91342 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 10/7/2021 | Approved | JOHN HAYES |
| Deputy Shotcrete | 10/15/2021 | Conditional Approval | JOHN HAYES |
| Deck | 5/10/2022 | Approved | JOHN HAYES |
| Enclosure/Fence | 6/8/2022 | Corrections Issued | JOHN HAYES |
| Enclosure/Fence | 6/13/2022 | Corrections Issued | JOHN HAYES |
| Enclosure/Fence | 6/24/2022 | Approved | ARAM AVEDISIAN |
| Equipment Noise Level | 8/31/2022 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 11/14/2022 | Approved | ARAM AVEDISIAN |
| Final | 11/14/2022 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 11/14/2022 | SGSOV Not Ready | ARAM AVEDISIAN |
| Final | 2/2/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Not Ready | ARAM AVEDISIAN |
| ELECTRICAL-Final | 2/21/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 2/21/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 2/21/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Final | 3/17/2023 | OK to Issue CofO | ARAM AVEDISIAN |
| PLUMBING-Final | 3/17/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/17/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 3/21/2023 | Corrections Issued | ARAM AVEDISIAN |