13274 W PARKLAND CIR 91342

Certificate Information: 13274 W PARKLAND CIR 91342

Application / Permit
21047-20000-01136
Plan Check / Job No.
B21VN06205
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW (53'-0"x 28'-7") POOL WITH A LAZY RIVER/BAJA AND 8' DIAMETER SPA PER STANDARD PLAN #268
Permit Issued
Issued on 7/12/2021
Issuing Office
Current Status
CofO Issued on 4/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2021 APPLICANT
Assigned to Plan Check Engineer 5/21/2021 PETER MOSESIAN
Corrections Issued 5/21/2021 PETER MOSESIAN
Building Plans Picked Up 5/25/2021 APPLICANT
Issued 7/12/2021 APPLICANT
CofO in Progress 3/17/2023 ARAM AVEDISIAN
No Progress 3/21/2023 ARAM AVEDISIAN
CofO in Progress 3/24/2023 ARAM AVEDISIAN
Permit Finaled 4/14/2023 MICHAEL SMITH
CofO Issued 4/14/2023 MICHAEL SMITH
Permit Finaled 4/14/2023 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Premier Pool Plastering; Lic. No.: 625132-C53 14520 FOOTHILL BLVD      SYLMAR, CA 91342
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 10/7/2021 Approved JOHN HAYES
Deputy Shotcrete 10/15/2021 Conditional Approval JOHN HAYES
Deck 5/10/2022 Approved JOHN HAYES
Enclosure/Fence 6/8/2022 Corrections Issued JOHN HAYES
Enclosure/Fence 6/13/2022 Corrections Issued JOHN HAYES
Enclosure/Fence 6/24/2022 Approved ARAM AVEDISIAN
Equipment Noise Level 8/31/2022 Approved FELIPE PENICHE
Excavation/Setback/Form/Re-Bar 11/14/2022 Approved ARAM AVEDISIAN
Final 11/14/2022 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 11/14/2022 SGSOV Not Ready ARAM AVEDISIAN
Final 2/2/2023 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/2/2023 SGSOV Not Ready ARAM AVEDISIAN
ELECTRICAL-Final 2/21/2023 Approved CHRISTOPHER DELLEFIELD
Final 2/21/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Final 2/21/2023 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 2/21/2023 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Final 3/17/2023 OK to Issue CofO ARAM AVEDISIAN
PLUMBING-Final 3/17/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV Approved ARAM AVEDISIAN
Special/Order Compliance 3/21/2023 Corrections Issued ARAM AVEDISIAN