1042 S STEARNS DR 90035

Certificate Information: 1042 S STEARNS DR 90035

Application / Permit
21047-20000-01091
Plan Check / Job No.
B21VN05979
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 14'-0" x 22'-0" POOL AND 10'-0" x 10'-0" SPA PER CITY STANDARD PLAN #268
Permit Issued
Issued on 8/12/2021
Issuing Office
Current Status
CofO Issued on 9/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 5/14/2021 ALFRED RAMIREZ
Corrections Issued 5/14/2021 ALFRED RAMIREZ
Issued 8/12/2021 APPLICANT
Building Plans Picked Up 8/12/2021 APPLICANT
CofO in Progress 9/9/2022 STUART CHAPMAN
Permit Finaled 9/11/2022 DEROLD HAUFF
CofO Issued 9/11/2022 DEROLD HAUFF
Permit Finaled 9/11/2022 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 6/14/2021 PABLO ESTRADA
ZI Cleared 6/14/2021 PABLO ESTRADA
Eng Process Fee Ord 176,300 Cleared 6/21/2021 WALLIE JONG
Miscellaneous Cleared 8/5/2021 ALBERT TAM

Contact Information

Contractor Pool Logic La; Lic. No.: 1053685-C53 1276 E COLORADO BLVD      PASADENA, CA 91106
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 8/26/2021 Approved KATHRYN BUTTERWORTH
Pre-Gunite 8/26/2021 Partial Approval KATHRYN BUTTERWORTH
Gas Piping or Gas Test 8/30/2021 Approved STUART CHAPMAN
Deck 9/2/2021 Corrections Issued FREDDIE RIVERA
Deck 9/10/2021 Approved STUART CHAPMAN
Enclosure/Fence 9/17/2021 Approved ALFREDO BALANDRA
Pool Equipment Noise Test 10/15/2021 Approved ROBERT CHAVEZ
Excavation/Setback/Form/Re-Bar 10/18/2021 Conditional Approval JOSE AVILA
Final 10/18/2021 Corrections Issued JOSE AVILA
Pre-Gunite 10/18/2021 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 10/18/2021 SGSOV Not Ready JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/22/2021 Not Ready for Inspection STUART CHAPMAN
Final 10/22/2021 Not Ready for Inspection STUART CHAPMAN
Pre-Gunite 10/22/2021 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/22/2021 SGSOV Not Ready STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 10/29/2021 Approved STUART CHAPMAN
Final 10/29/2021 Conditional Approval STUART CHAPMAN
Pre-Gunite 10/29/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/29/2021 SGSOV Approved STUART CHAPMAN
Final 9/8/2022 OK to Issue CofO STUART CHAPMAN