6601 N FIRMAMENT AVE 91406

Certificate Information: 6601 N FIRMAMENT AVE 91406

Application / Permit
21047-20000-01089
Plan Check / Job No.
B21VN05977
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 14'-0" x 28'-0" POOL AND 8'-0" x 9'-0" SPA PER CITY STANDARD PLAN #268
Permit Issued
Issued on 8/30/2021
Issuing Office
Current Status
CofO Issued on 2/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 5/14/2021 ALFRED RAMIREZ
Corrections Issued 5/14/2021 ALFRED RAMIREZ
Issued 8/30/2021 APPLICANT
Building Plans Picked Up 8/31/2021 APPLICANT
CofO in Progress 2/7/2023 RYAN SALAZAR
CofO Issued 2/17/2023 MICHAEL SMITH
Permit Finaled 2/17/2023 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 8/19/2021 RIDWAN HARDY

Contact Information

Contractor Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 978 NORTH AMEILA AVE      SAN DIMAS, CA 91773
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 10/27/2021 Approved RICHARD DOCKUS
Deck 11/2/2022 Corrections Issued JENNIFER RABUCHIN
Enclosure/Fence 11/2/2022 Corrections Issued JENNIFER RABUCHIN
Deck 12/2/2022 Approved RYAN SALAZAR
Enclosure/Fence 12/2/2022 Corrections Issued RYAN SALAZAR
Pool Equipment Noise Test 12/9/2022 Not Ready for Inspection ALFREDO FLORES
Equipment Noise Level 12/13/2022 Approved FELIPE PENICHE
Excavation/Setback/Form/Re-Bar 12/19/2022 Approved RYAN SALAZAR
Final 12/19/2022 Corrections Issued RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Approved RYAN SALAZAR
ELECTRICAL-Final 1/17/2023 Approved RYAN SALAZAR
Final 1/17/2023 Partial Approval RYAN SALAZAR
Pool Equipment Noise Test 1/17/2023 No Access for Inspection FELIPE PENICHE
Final 1/26/2023 Partial Approval RYAN SALAZAR
Final 2/7/2023 OK to Issue CofO RYAN SALAZAR