4122 N COLBATH AVE 91423
Certificate Information: 4122 N COLBATH AVE 91423
- Application / Permit
- 21047-20000-01064
- Plan Check / Job No.
- B21VN05845
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 10' x 45' POOL W/ 5' x 7' SPA PER LA CITY PRE-APPROVED STANDARD PLAN #242
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | SEAN SHAHMIRI |
| Corrections Issued | 6/15/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 6/21/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/25/2021 | APPLICANT |
| Plan Check Approved | 5/31/2022 | SEAN SHAHMIRI |
| Issued | 6/10/2022 | APPLICANT |
| CofO in Progress | 5/13/2024 | MISAEL ESPARZA |
| Permit Finaled | 6/5/2024 | RUBEN SALAS |
| CofO Issued | 6/5/2024 | RUBEN SALAS |
| Permit Finaled | 6/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/4/2022 | RIDWAN HARDY |
Contact Information
| Contractor | S & S Pool Company; Lic. No.: 949249-C53 | 30135 MADLOY STREET CASTAIC, CA 91384 |
| Engineer | Shniderman,, Jason Bernard; Lic. No.: C20524 | 16000 SHERMAN WAY #234 VAN NUYS, CA 91607 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/27/2022 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 8/18/2022 | Approved | MISAEL ESPARZA |
| Grounding or Bonding | 8/18/2022 | Partial Approval | MISAEL ESPARZA |
| Pre-Gunite | 8/18/2022 | Approved | MISAEL ESPARZA |
| Deputy Shotcrete | 8/24/2022 | Conditional Approval | MISAEL ESPARZA |
| Grounding or Bonding | 1/17/2024 | Approved | MISAEL ESPARZA |
| Gas Piping or Gas Test | 3/18/2024 | Corrections Issued | THOMAS FINNILA |
| Gas Piping or Gas Test | 3/26/2024 | Approved | MISAEL ESPARZA |
| Rough-Electrical | 3/26/2024 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 4/19/2024 | Corrections Issued | MISAEL ESPARZA |
| Pre-Inspection | 4/19/2024 | Approved | MISAEL ESPARZA |
| Pool Equipment Noise Test | 5/3/2024 | Approved | FELIPE PENICHE |
| Final | 5/8/2024 | OK to Issue CofO | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/8/2024 | SGSOV Approved | MISAEL ESPARZA |