145 N LAYTON DR 90049
Certificate Information: 145 N LAYTON DR 90049
- Application / Permit
- 21047-20000-01062
- Plan Check / Job No.
- B21VN05843
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL (54'-0" X18'-6") NEW SPA (10'-6"x 8'-0") PER STANDARD PLAN #270
- Permit Issued
- Issued on 10/6/2021
- Issuing Office
- Current Status
- CofO Issued on 9/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | PETER MOSESIAN |
| Corrections Issued | 5/29/2021 | PETER MOSESIAN |
| Quality Review Completed | 6/2/2021 | OMID HEDAYAT |
| Plan Check Approved | 10/6/2021 | PETER MOSESIAN |
| Issued | 10/6/2021 | APPLICANT |
| CofO in Progress | 9/12/2025 | CARLOS MATAMOROS |
| Permit Finaled | 9/18/2025 | RICHARD STEINBACH |
| CofO Issued | 9/18/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/18/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2021 | MAHELET GEBEYHU |
| Watercourse | Cleared | 8/2/2021 | MAHELET GEBEYHU |
Contact Information
| Contractor | Wavecrest Pools Inc; Lic. No.: 881346-C53 | 5320 DERRY AVENUE SUITE B AGOURA HILLS, CA 91301 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Proofing Certificate | 2/22/2022 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 2/22/2022 | Approved | CARLOS MATAMOROS |
| Pool Piping | 2/22/2022 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 2/22/2022 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Shotcrete | 2/23/2022 | Conditional Approval | CARLOS MATAMOROS |
| Enclosure/Fence | 9/11/2024 | Approved | CARLOS MATAMOROS |
| Equipment Noise Level | 9/24/2024 | Approved | EUSEBIO GUZMAN |
| Excavation/Setback/Form/Re-Bar | 4/24/2025 | Approved | CARLOS MATAMOROS |
| FLOOD-Elevation Certificate | 4/24/2025 | Approved | CARLOS MATAMOROS |
| Final | 4/24/2025 | Corrections Issued | CARLOS MATAMOROS |
| Pre-Gunite | 4/24/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 4/24/2025 | SGSOV Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 4/28/2025 | Approved | CARLOS MATAMOROS |
| Final | 4/28/2025 | Conditional Approval | CARLOS MATAMOROS |
| Final | 9/11/2025 | OK to Issue CofO | CARLOS MATAMOROS |
| PLUMBING-Final | 9/11/2025 | Approved | CARLOS MATAMOROS |