20372 W LIVERPOOL WAY 91326
Certificate Information: 20372 W LIVERPOOL WAY 91326
- Application / Permit
- 21047-20000-00975
- Plan Check / Job No.
- B21VN05347
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 37' 6" X 21' 9" IRR.-SHAPE SWIMMING POOL PER LA CITY STANDARD PLAN #268 AND ENGINEERED DETAIL #520, #551, #651, #668
- Permit Issued
- Issued on 8/13/2021
- Issuing Office
- Current Status
- CofO Issued on 3/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 5/9/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 8/12/2021 | GURUNATH NESARAJAH |
| Issued | 8/13/2021 | APPLICANT |
| Building Plans Picked Up | 8/17/2021 | APPLICANT |
| CofO in Progress | 8/1/2022 | DAVID SCANTLIN |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
| CofO Issued | 3/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| "T" removal | Cleared | 7/26/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 7/26/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 7/26/2021 | DANG NGUYEN |
| Specific Plan | Cleared | 7/26/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 7/26/2021 | DANG NGUYEN |
| ZI | Cleared | 7/26/2021 | DANG NGUYEN |
| ZI | Cleared | 7/26/2021 | DANG NGUYEN |
Contact Information
| Contractor | Pool Logic La; Lic. No.: 1053685-C53 | 1276 E COLORADO BLVD PASADENA, CA 91106 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Enclosure/Fence | 3/31/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Enclosure/Fence | 4/6/2022 | Corrections Issued | SEAN WIRCH |
| Enclosure/Fence | 4/11/2022 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 5/12/2022 | Approved | DAVID SCANTLIN |
| Final | 5/12/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Pre-Gunite | 5/12/2022 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Approved | DAVID SCANTLIN |
| Pre-Inspection | 5/16/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 5/17/2022 | Corrections Issued | DAVID SCANTLIN |
| Equipment Noise Level | 5/19/2022 | Approved | ALFREDO FLORES |
| Pool Equipment Noise Test | 5/19/2022 | Approved | ALFREDO FLORES |
| Final | 5/23/2022 | Corrections Issued | DAVID SCANTLIN |
| Final | 7/28/2022 | OK to Issue CofO | DAVID SCANTLIN |