6961 N DARNOCH WAY 91307
Certificate Information: 6961 N DARNOCH WAY 91307
- Application / Permit
- 21047-20000-00946
- Plan Check / Job No.
- B21VN05164
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 20'-0" x 32'-0" POOL AND 9'-0" x 9'-0" SPA WITH BAJA AND POOL COVER VAULT PER CITY STANDARD CITY PLAN #268 AND ENGINEERING DETAILS.
- Permit Issued
- Issued on 5/10/2021
- Issuing Office
- Current Status
- CofO Issued on 1/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | ALFRED RAMIREZ |
| Corrections Issued | 4/29/2021 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 5/7/2021 | ALFRED RAMIREZ |
| Issued | 5/10/2021 | APPLICANT |
| Building Plans Picked Up | 5/12/2021 | APPLICANT |
| CofO in Progress | 12/1/2021 | TROY SANDERS |
| Permit Finaled | 1/12/2022 | JOHN JANSON |
| CofO Issued | 1/12/2022 | JOHN JANSON |
| Permit Finaled | 1/12/2022 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/29/2021 | ALFRED RAMIREZ |
Contact Information
| Contractor | Aqua Escapes Inc; Lic. No.: 1029678-C53 | 8808 DEMPSEY AVE NORTH HILLS, CA 91343 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/1/2021 | Corrections Issued | TROY SANDERS |
| Grading Pre-Inspection | 6/7/2021 | Corrections Issued | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 6/10/2021 | Approved | DAVID SANDOVAL |
| Pool Piping | 6/10/2021 | Corrections Issued | DAVID SANDOVAL |
| Pool Piping | 6/11/2021 | Approved | PETER FOLLING |
| Pre-Gunite | 6/11/2021 | Approved | PETER FOLLING |
| Grounding or Bonding | 7/23/2021 | Partial Approval | DAVID STEPANYAN |
| Pre-Inspection | 7/23/2021 | Corrections Issued | DAVID STEPANYAN |
| Enclosure/Fence | 9/3/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Final | 9/3/2021 | Corrections Issued | DAVID STEPANYAN |
| Enclosure/Fence | 9/9/2021 | Approved | DAVID STEPANYAN |
| Equipment Noise Level | 9/28/2021 | Approved | ALFREDO FLORES |
| Final | 10/27/2021 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2021 | SGSOV Not Required | DAVID STEPANYAN |
| Final | 11/3/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Final | 12/1/2021 | Approved | TROY SANDERS |
| Final | 12/1/2021 | OK to Issue CofO | TROY SANDERS |
| Special/Order Compliance | 12/28/2021 | Approved | TROY SANDERS |