7024 N VAN NOORD AVE 91605
Certificate Information: 7024 N VAN NOORD AVE 91605
- Application / Permit
- 21047-20000-00927
- Plan Check / Job No.
- B21VN04992
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 25' x 14' POOL AND 9' x 14' SPA PER LA CITY STANDARD PLAN #265 *** SEE COMMENTS
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2021 | OMAR GARNICA |
| Plan Check Approved | 4/27/2021 | OMAR GARNICA |
| Issued | 10/28/2021 | APPLICANT |
| Building Plans Picked Up | 11/1/2021 | APPLICANT |
| CofO in Progress | 11/14/2022 | CALEB MEISTER |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
| CofO Issued | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/10/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Pool Piping | 11/10/2021 | Approved | CHRISTOPHE COCHRAN |
| Pre-Gunite | 11/10/2021 | Approved | CHRISTOPHE COCHRAN |
| Rough-Electrical | 11/10/2021 | Approved | CHRISTOPHE COCHRAN |
| Gas Piping or Gas Test | 1/11/2022 | Approved | CHRISTOPHE COCHRAN |
| Grounding or Bonding | 6/30/2022 | Conditional Approval | RAFAEL CORTES |
| Enclosure/Fence | 8/10/2022 | Corrections Issued | RAFAEL CORTES |
| ELECTRICAL-Final | 8/16/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Enclosure/Fence | 8/16/2022 | Approved | RAFAEL CORTES |
| Pool Equipment Noise Test | 9/8/2022 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 10/28/2022 | Approved | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 10/28/2022 | Approved | CALEB MEISTER |
| Final | 10/28/2022 | Conditional Approval | CALEB MEISTER |
| PLUMBING-Final | 10/28/2022 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 10/28/2022 | SGSOV Approved | CALEB MEISTER |
| Final | 11/10/2022 | OK to Issue CofO | CALEB MEISTER |