4228 W LOS NIETOS DR 90027
Certificate Information: 4228 W LOS NIETOS DR 90027
- Application / Permit
- 21047-20000-00908
- Plan Check / Job No.
- B21VN04943
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 11'-0" X 22'-0" SWIMMING POOL PER STD PLAN # 268 AND ENGINEERING DETAILS.
- Permit Issued
- Issued on 6/8/2021
- Issuing Office
- Current Status
- CofO Issued on 7/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 5/1/2021 | ARTIN ZARUKIAN |
| Plan Check Approved | 6/8/2021 | ARTIN ZARUKIAN |
| Issued | 6/8/2021 | APPLICANT |
| Building Plans Picked Up | 6/14/2021 | APPLICANT |
| CofO in Progress | 6/27/2022 | JOSEPH MCGARRY |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
| CofO Issued | 7/9/2022 | DEROLD HAUFF |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Pool Logic La; Lic. No.: 1053685-C53 | 1276 E COLORADO BLVD PASADENA, CA 91106 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/20/2021 | Approved | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 10/20/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Grounding or Bonding | 10/20/2021 | Approved | JOSEPH MCGARRY |
| Pool Piping | 10/20/2021 | Approved | JOSEPH MCGARRY |
| Pre-Gunite | 10/20/2021 | Approved | JOSEPH MCGARRY |
| Rough-Electrical | 10/20/2021 | Approved | JOSEPH MCGARRY |
| Deck | 11/3/2021 | Approved | JOSEPH MCGARRY |
| Grading Pre-Inspection | 11/24/2021 | Partial Approval | JOSEPH MCGARRY |
| Enclosure/Fence | 2/7/2022 | Approved | JOSEPH MCGARRY |
| Final | 3/10/2022 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/10/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Final | 3/16/2022 | Corrections Issued | JOSEPH MCGARRY |
| Final | 6/21/2022 | OK to Issue CofO | JOSEPH MCGARRY |