1746 S CRESCENT HEIGHTS BLVD 90035
Certificate Information: 1746 S CRESCENT HEIGHTS BLVD 90035
- Application / Permit
- 21047-20000-00884
- Plan Check / Job No.
- B21VN04834
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 20.33'-0" x 15'-0" POOL WITH 6'-0" x 5'-0" SPA PER LA CITY STANDARD PLAN# 265.
- Permit Issued
- Issued on 9/6/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 5/1/2021 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 7/26/2021 | APPLICANT |
| Applicant returned to address corrections | 7/22/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 9/6/2022 | RAMA DABADGE |
| Issued | 9/6/2022 | APPLICANT |
| CofO in Progress | 9/26/2024 | ARTHUR NEGRETE |
| Permit Finaled | 4/5/2025 | DEROLD HAUFF |
| CofO Issued | 4/5/2025 | DEROLD HAUFF |
| Permit Finaled | 4/5/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2021 | JEANIE LAM |
| Construction near power lines | Cleared | 6/22/2022 | TINA MIRANDA |
| Construction within easement | Cleared | 6/22/2022 | TINA MIRANDA |
| Encroachment in public way | Cleared | 6/28/2022 | JEREMY CHOK |
| Work Adjacent to Public Way | Cleared | 7/26/2022 | ARMEN SARKISIAN |
Contact Information
| Contractor | California Home Remodeling; Lic. No.: 998940-B | 15335 MORRISON STREET #345 SHERMAN OAKS, CA 91403 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 11/1/2022 | Off-Hour Fees Due | |
| Pre-Inspection | 11/1/2022 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 12/6/2022 | Corrections Issued | JOSE AVILA |
| Rough-Electrical | 12/6/2022 | Not Ready for Inspection | JOSE AVILA |
| Rough-Plumbing | 12/6/2022 | Not Ready for Inspection | JOSE AVILA |
| Pool Piping | 2/8/2023 | Partial Approval | JOSE AVILA |
| Rough-Electrical | 2/8/2023 | Corrections Issued | JOSE AVILA |
| Grading Pre-Inspection | 2/15/2023 | Approved | JOSE AVILA |
| Gunite | 3/8/2023 | Approved | JOSE AVILA |
| Grounding or Bonding | 3/15/2023 | No Access for Inspection | JOSEPH MCGARRY |
| Grounding or Bonding | 3/23/2023 | No Access for Inspection | JOSE AVILA |
| Pool Equipment Noise Test | 4/10/2023 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| Pool Equipment Noise Test | 4/20/2023 | Not Ready for Inspection | ZEYDI STEWART |
| Enclosure/Fence | 4/22/2023 | Corrections Issued | SEAN HAUPT |
| Deck | 4/25/2023 | Corrections Issued | JOSE AVILA |
| Enclosure/Fence | 4/25/2023 | Approved | JOSE AVILA |
| Enclosure/Fence | 4/26/2023 | Approved | JOSE AVILA |
| Equipment Noise Level | 5/4/2023 | Approved | JUAN ESCOTO DELGADO |
| Special/Order Compliance | 6/8/2023 | Corrections Issued | JOSE AVILA |
| Final | 6/22/2023 | Not Ready for Inspection | JOSE AVILA |
| Pre-Gunite | 6/22/2023 | Not Ready for Inspection | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Not Ready | JOSE AVILA |
| Special/Order Compliance | 6/22/2023 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 8/10/2023 | Approved | JOSE AVILA |
| Pre-Gunite | 8/10/2023 | Approved | JOSE AVILA |
| Final | 11/6/2023 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/6/2023 | SGSOV Approved | JOSE AVILA |
| Final | 11/21/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 12/1/2023 | Corrections Issued | JOSE AVILA |
| Final | 12/12/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 12/18/2023 | Corrections Issued | SCOTT FINNILA |
| Final | 9/24/2024 | OK to Issue CofO | ARTHUR NEGRETE |