2493 N DEVONPORT LANE 90077
Certificate Information: 2493 N DEVONPORT LANE 90077
- Application / Permit
- 21047-20000-00871
- Plan Check / Job No.
- B21VN04762
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 8' X 26' SWIMMING POOL AND 10' X 8' SPA PER STANDARD PLAN # 265
- Permit Issued
- Issued on 9/28/2021
- Issuing Office
- Current Status
- CofO Issued on 9/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 4/22/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 5/15/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/19/2021 | APPLICANT |
| Applicant returned to address corrections | 7/29/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 9/23/2021 | JEROME MAGAT PALMA |
| Issued | 9/28/2021 | APPLICANT |
| CofO in Progress | 8/18/2022 | CARLOS MATAMOROS |
| CofO Issued | 9/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/22/2021 | JEFFREY TANGONAN |
| "Q" conditions | Cleared | 5/18/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 5/18/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 5/18/2021 | DANG NGUYEN |
| ZA Case | Cleared | 5/18/2021 | DANG NGUYEN |
Contact Information
| Contractor | Ahern Construction Corporation; Lic. No.: 687780-C53 | 3835-R THOUSAND OAKS BLVD #118 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Proofing Certificate | 11/5/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Pre-Gunite | 11/5/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 11/5/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Deputy Shotcrete | 11/12/2021 | Conditional Approval | STEPHANIE SWANSON |
| Deck | 3/14/2022 | Approved | OGANES TARAKHCHYAN |
| Enclosure/Fence | 6/15/2022 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 7/6/2022 | Partial Approval | CARLOS MATAMOROS |
| FLOOD-Elevation Certificate | 7/6/2022 | Approved | CARLOS MATAMOROS |
| Final | 7/6/2022 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 7/6/2022 | SGSOV Approved | CARLOS MATAMOROS |
| Equipment Noise Level | 7/7/2022 | Approved | ROBERT CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 7/14/2022 | Approved | CARLOS MATAMOROS |
| Final | 7/14/2022 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/16/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 8/16/2022 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 8/16/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/17/2022 | Approved | CARLOS MATAMOROS |
| Final | 8/17/2022 | OK to Issue CofO | CARLOS MATAMOROS |