19210 W LULL ST 91335
Certificate Information: 19210 W LULL ST 91335
- Application / Permit
- 21047-20000-00858
- Plan Check / Job No.
- B21VN04662
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 30' X 15' SWIMMING POOL WITH ATTACHED 7' X 7' SPA PER LA CITY STANDARD PLAN # 270
- Permit Issued
- Issued on 7/12/2021
- Issuing Office
- Current Status
- CofO Issued on 3/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 6/9/2021 | GURUNATH NESARAJAH |
| Issued | 7/12/2021 | APPLICANT |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| CofO in Progress | 3/18/2022 | VINCENT HANLEY |
| Permit Finaled | 3/25/2022 | DEROLD HAUFF |
| CofO Issued | 3/25/2022 | DEROLD HAUFF |
| Permit Finaled | 3/25/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Royal Moon Pools Inc; Lic. No.: 1041907-C53 | 2518 SAN MACHID WAY ROSAMOND, CA 93560 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 7/19/2021 | Approved | RONALD COWAN |
| Deck | 8/17/2021 | Corrections Issued | DAVID SANDOVAL |
| Grounding or Bonding | 8/17/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Deck | 8/23/2021 | Partial Approval | PETER FOLLING |
| Grounding or Bonding | 8/23/2021 | Partial Approval | PETER FOLLING |
| Deck | 9/20/2021 | Corrections Issued | VINCENT HANLEY |
| Enclosure/Fence | 9/20/2021 | Corrections Issued | VINCENT HANLEY |
| Grounding or Bonding | 9/20/2021 | Corrections Issued | VINCENT HANLEY |
| Deck | 9/22/2021 | Approved | VINCENT HANLEY |
| Enclosure/Fence | 9/22/2021 | Approved | VINCENT HANLEY |
| Grounding or Bonding | 9/22/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 10/18/2021 | SGSOV Not Ready | DAVID STEPANYAN |
| Final | 10/20/2021 | Corrections Issued | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 12/7/2021 | Approved | VINCENT HANLEY |
| Final | 12/7/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Pool Equipment Noise Test | 12/7/2021 | Approved | ALFREDO FLORES |
| SGSOV-Seismic Gas S/O Valve | 12/7/2021 | SGSOV Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 12/10/2021 | Approved | VINCENT HANLEY |
| Final | 12/10/2021 | Partial Inspection | VINCENT HANLEY |
| Final | 3/18/2022 | OK to Issue CofO | VINCENT HANLEY |