10020 N RUDNICK AVE 91311
Certificate Information: 10020 N RUDNICK AVE 91311
- Application / Permit
- 21047-20000-00843
- Plan Check / Job No.
- B21VN04575
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16' X 34' POOL AND 8' X 7' SPA. PER LA CITY STANDARD No. 268
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- CofO Issued on 9/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 4/19/2021 | LUISANGEL VALENZUELA |
| Plan Check Approved | 5/12/2021 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 5/13/2021 | APPLICANT |
| Issued | 5/24/2021 | APPLICANT |
| CofO in Progress | 9/27/2021 | DAVID STEPANYAN |
| CofO Issued | 9/27/2021 | JOHN JANSON |
| Permit Finaled | 9/27/2021 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/19/2021 | LUISANGEL VALENZUELA |
Contact Information
| Contractor | Elemental Construction Inc; Lic. No.: 1014393-C53 | 2629 TOWNSGATE RD #235 WESTLAKE VILLAGE, CA 913612987 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/21/2021 | Approved | DAVID STEPANYAN |
| Grounding or Bonding | 6/21/2021 | Partial Approval | DAVID STEPANYAN |
| Pool Piping | 6/21/2021 | Approved | DAVID STEPANYAN |
| Pre-Gunite | 6/21/2021 | Approved | DAVID STEPANYAN |
| Rough-Electrical | 6/21/2021 | Partial Approval | DAVID STEPANYAN |
| Deputy Shotcrete | 6/23/2021 | Approved | SHAVONNE ESPINOZA |
| Deck | 7/21/2021 | Approved | DAVID SCANTLIN |
| Enclosure/Fence | 8/3/2021 | Corrections Issued | DAVID STEPANYAN |
| Enclosure/Fence | 8/10/2021 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Final | 9/24/2021 | Approved | DAVID STEPANYAN |
| Enclosure/Fence | 9/24/2021 | Approved | DAVID STEPANYAN |
| Final | 9/24/2021 | OK to Issue CofO | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 9/24/2021 | SGSOV Approved | DAVID STEPANYAN |
| Special/Order Compliance | 9/24/2021 | Partial Approval | DAVID STEPANYAN |