1914 N VAN NESS AVE 90068
Certificate Information: 1914 N VAN NESS AVE 90068
- Application / Permit
- 21047-20000-00741
- Plan Check / Job No.
- B21VN03975
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14' X 23'-10" POOL AND SPA 6' X 6' SPA W/ AUTO POOL COVER PER STANDARD PLAN #268
- Permit Issued
- Issued on 9/28/2021
- Issuing Office
- Current Status
- CofO Issued on 7/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2021 | RAPHAEL ROSAS |
| Corrections Issued | 4/6/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 9/2/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 9/22/2021 | APPLICANT |
| Issued | 9/28/2021 | APPLICANT |
| CofO in Progress | 6/9/2022 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 7/6/2022 | DEROLD HAUFF |
| CofO Issued | 7/6/2022 | DEROLD HAUFF |
| Permit Finaled | 7/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 4/14/2021 | PABLO ESTRADA |
| Miscellaneous | Cleared | 4/14/2021 | PABLO ESTRADA |
| ZI | Cleared | 4/14/2021 | PABLO ESTRADA |
| Construction near power lines | Cleared | 8/12/2021 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 9/2/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | Fletcher Pools; Lic. No.: 764765-C53 | 17429 CHASE STREET NORTHRIDGE, CA 91325 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/27/2021 | Approved | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 10/27/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Grounding or Bonding | 10/27/2021 | Approved | JOSEPH MCGARRY |
| Pool Piping | 10/27/2021 | Approved | JOSEPH MCGARRY |
| Pre-Gunite | 10/27/2021 | Conditional Approval | JOSEPH MCGARRY |
| Deputy Shotcrete | 10/29/2021 | Partial Approval | JOSEPH MCGARRY |
| Rough-Electrical | 4/13/2022 | Corrections Issued | SCOTT FINNILA |
| Enclosure/Fence | 5/12/2022 | Corrections Issued | BRIAN SULLIVAN |
| Enclosure/Fence | 5/18/2022 | Approved | JOSEPH MCGARRY |
| Final | 6/8/2022 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Gunite | 6/8/2022 | Approved | ALEJANDRO DE ARTOLA |
| Pool Equipment Noise Test | 6/8/2022 | Approved | JUSTIN CURTIS |
| Pre-Gunite | 6/8/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 6/8/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |