11573 N ZELZAH AVE 91344
Certificate Information: 11573 N ZELZAH AVE 91344
- Application / Permit
- 21047-20000-00684
- Plan Check / Job No.
- B21VN03662
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 33'-0" x 16'-0" POOL WITH 7'-0" IN DIAMETER SPA PER LA CITY STANDARD PLANS #268
- Permit Issued
- Issued on 7/14/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | ALFREDO JARA |
| Corrections Issued | 4/6/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 4/16/2021 | KHUONG TRUONG |
| Plan Check Approved | 7/2/2021 | SARKIS HARABEDIAN |
| Issued | 7/14/2021 | APPLICANT |
| CofO in Progress | 3/25/2022 | DAVID SCANTLIN |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
| CofO Issued | 9/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/30/2021 | ALFREDO JARA |
Contact Information
| Contractor | Swan Pools West; Lic. No.: 642775-C53 | 4525 LUBBOCK DRIVE SIMI VALLEY, CA 93063 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 8/2/2021 | Approved | DAVID SCANTLIN |
| Deputy Shotcrete | 8/5/2021 | Partial Approval | DAVID SCANTLIN |
| Gas Piping or Gas Test | 9/14/2021 | Approved | DAVID SCANTLIN |
| Rough-Electrical | 9/14/2021 | Approved | DAVID SCANTLIN |
| Grounding or Bonding | 9/20/2021 | Approved | DAVID SCANTLIN |
| Enclosure/Fence | 11/22/2021 | Corrections Issued | DAVID SCANTLIN |
| Enclosure/Fence | 12/6/2021 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 2/28/2022 | Approved | DAVID SCANTLIN |
| Final | 2/28/2022 | No Access for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2022 | SGSOV Not Ready | DAVID SCANTLIN |
| Pool Equipment Noise Test | 3/2/2022 | Approved | ALFREDO FLORES |
| ELECTRICAL-Final | 3/4/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 3/4/2022 | Approved | DAVID SCANTLIN |
| Final | 3/24/2022 | OK to Issue CofO | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/24/2022 | SGSOV Approved | DAVID SCANTLIN |