13525 W ROMANY DR 90272
Certificate Information: 13525 W ROMANY DR 90272
- Application / Permit
- 21047-20000-00664
- Plan Check / Job No.
- B21VN03560
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 18' X 38' SWIMMING POOL WITH ATTACHED 7' X 9' SPA PER LA CITY STANDARD PLAN #265 AND ENGINEERED DETAILS
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Current Status
- CofO Issued on 1/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 3/29/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/19/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 5/20/2021 | APPLICANT |
| Issued | 8/9/2021 | APPLICANT |
| CofO in Progress | 1/3/2023 | JUAN VALENZUELA |
| Permit Finaled | 1/7/2023 | DANIEL ORRANTE |
| CofO Issued | 1/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/9/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Pool Piping | 9/9/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Gunite | 9/9/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Rough-Electrical | 9/9/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Rough-Plumbing | 9/9/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pool Piping | 9/28/2021 | Approved | JOHN KIDWELL |
| Pre-Gunite | 9/28/2021 | Approved | JOHN KIDWELL |
| Deputy Other (see comments) | 10/12/2021 | No Access for Inspection | KENNETH NAGLE |
| Gas Piping or Gas Test | 11/1/2021 | Approved | ANDREW NAVE |
| Pool Piping | 11/1/2021 | Approved | ANDREW NAVE |
| Rough-Electrical | 11/1/2021 | Approved | ANDREW NAVE |
| Rough-Plumbing | 11/1/2021 | Approved | ANDREW NAVE |
| Grounding or Bonding | 4/4/2022 | Approved | MICHAEL PELHAM |
| Enclosure/Fence | 10/26/2022 | Approved | JUAN VALENZUELA |
| Equipment Noise Level | 12/14/2022 | Approved | AGUSTIN ALVAREZMORALES |
| ELECTRICAL-Final | 12/15/2022 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 12/15/2022 | Approved | EVAN COOPER |
| Final | 12/15/2022 | Conditional Approval | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/15/2022 | SGSOV Approved | EVAN COOPER |