425 N PARKWOOD DR 90077

Certificate Information: 425 N PARKWOOD DR 90077

Application / Permit
21047-20000-00648
Plan Check / Job No.
B21VN03481
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 51' X 25'-6" SWIMMING POOL AND 10'-6" X 10'-6" SPA PER STANDARD PLAN #268 AND ENGINEER DETAIL
Permit Issued
Issued on 3/25/2021
Issuing Office
Current Status
CofO Issued on 6/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 JEROME MAGAT PALMA
Corrections Issued 3/25/2021 JEROME MAGAT PALMA
Issued 3/25/2021 APPLICANT
CofO in Progress 6/5/2023 CHRISTOPHER WILSON
CofO in Progress 6/5/2023 CHRISTOPHER WILSON
Permit Finaled 6/6/2023 DANIEL ORRANTE
CofO Issued 6/6/2023 DANIEL ORRANTE
Permit Finaled 6/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/25/2021 JEROME MAGAT PALMA

Contact Information

Contractor Ventura Pools & Masonry; Lic. No.: 880479-C53 19600 STRATHERN ST      RESEDA, CA 91335
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 6/11/2021 Approved GERMAN RODRIGUEZ MENDOZA
Pre-Gunite 6/22/2021 Corrections Issued CHRISTOPHER WILSON
Pre-Gunite 7/1/2021 Not Ready for Inspection CHRISTOPHER WILSON
Grounding or Bonding 7/13/2021 Partial Approval CHRISTOPHER WILSON
Pool Piping 7/13/2021 Approved CHRISTOPHER WILSON
Pre-Gunite 7/13/2021 Approved CHRISTOPHER WILSON
Rough-Electrical 7/13/2021 Partial Approval CHRISTOPHER WILSON
Grounding or Bonding 9/8/2022 Corrections Issued STEPHANIE SWANSON
Grounding or Bonding 9/12/2022 Partial Approval CHRISTOPHER WILSON
Grounding or Bonding 9/15/2022 Corrections Issued CHRISTOPHER WILSON
Grounding or Bonding 9/20/2022 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 10/21/2022 Partial Approval CHRISTOPHER WILSON
Enclosure/Fence 4/11/2023 Corrections Issued CHRISTOPHER WILSON
Grounding or Bonding 4/11/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/25/2023 Approved CHRISTOPHER WILSON
Final 4/25/2023 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 4/25/2023 SGSOV Approved CHRISTOPHER WILSON
Final 4/28/2023 Corrections Issued CHRISTOPHER WILSON
Enclosure/Fence 5/8/2023 Approved CHRISTOPHER WILSON
Final 6/2/2023 OK to Issue CofO CHRISTOPHER WILSON