4103 N CAMELLIA AVE 91604

Certificate Information: 4103 N CAMELLIA AVE 91604

Application / Permit
21047-20000-00634
Plan Check / Job No.
B21VN03384
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 11' X 26' SWIMMING POOL WITH ATTACHED 11' X 5' SPA PER LA CITY STANDARD PLAN #268 AND ENGINEERED DETAIL #271 & #672
Permit Issued
Issued on 4/15/2021
Issuing Office
Current Status
CofO Issued on 6/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2021 APPLICANT
Assigned to Plan Check Engineer 3/24/2021 GURUNATH NESARAJAH
Corrections Issued 3/24/2021 GURUNATH NESARAJAH
Plan Check Approved 4/14/2021 GURUNATH NESARAJAH
Issued 4/15/2021 APPLICANT
Building Plans Picked Up 4/19/2021 APPLICANT
CofO in Progress 6/15/2022 DAVID MATSON
CofO in Progress 6/15/2022 DAVID MATSON
CofO Issued 6/15/2022 MICHAEL SMITH
Permit Finaled 6/15/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 4/6/2021 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/20/2021 Corrections Issued THOMAS FINNILA
Pre-Gunite 9/20/2021 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 9/23/2021 Approved ARAM AVEDISIAN
Grounding or Bonding 9/23/2021 Partial Approval ARAM AVEDISIAN
Pool Piping 9/23/2021 Approved ARAM AVEDISIAN
Pre-Gunite 9/23/2021 Approved ARAM AVEDISIAN
Grounding or Bonding 3/8/2022 Approved RYAN SALAZAR
Enclosure/Fence 4/6/2022 Corrections Issued THOMAS FINNILA
Enclosure/Fence 4/25/2022 Corrections Issued THOMAS FINNILA
Enclosure/Fence 5/6/2022 Approved DAVID MATSON
Equipment Noise Level 5/11/2022 Approved FELIPE PENICHE
Pool Equipment Noise Test 5/11/2022 Approved FELIPE PENICHE
Final 6/14/2022 OK to Issue CofO DAVID MATSON
SGSOV-Seismic Gas S/O Valve 6/14/2022 SGSOV Not Required DAVID MATSON