20312 W HOWARD CT 91364
Certificate Information: 20312 W HOWARD CT 91364
- Application / Permit
- 21047-20000-00629
- Plan Check / Job No.
- B21VN03368
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW IRR SHAPED 50'X25' SWIMMING POOL W/ 8' DIA SPA PER CITY STD PLAN #268.
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- CofO Issued on 5/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 4/16/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 5/11/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 5/24/2021 | HAYATO TSUCHIYA |
| Issued | 5/24/2021 | APPLICANT |
| Building Plans Picked Up | 5/25/2021 | APPLICANT |
| CofO in Progress | 5/4/2022 | PETER FOLLING |
| CofO Issued | 5/18/2022 | MICHAEL SMITH |
| Permit Finaled | 5/18/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2021 | GABRIEL ROBLES |
| Specific Plan | Cleared | 5/5/2021 | DANG NGUYEN |
| Watercourse | Cleared | 5/7/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Vargas Excavating Inc; Lic. No.: 639939-C53 | 501 SO REINO ROAD # 338 NEWBURY PARK, CA 91320 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 8/20/2021 | Approved | PETER FOLLING |
| Pre-Gunite | 8/20/2021 | Approved | PETER FOLLING |
| Deputy Shotcrete | 8/24/2021 | Conditional Approval | RYAN SALAZAR |
| Gas Piping or Gas Test | 9/13/2021 | Approved | PETER FOLLING |
| Rough-Electrical | 9/13/2021 | Approved | PETER FOLLING |
| Grounding or Bonding | 11/16/2021 | Approved | PETER FOLLING |
| Enclosure/Fence | 4/20/2022 | Approved | PETER FOLLING |
| Excavation/Setback/Form/Re-Bar | 4/28/2022 | Approved | PETER FOLLING |
| Final | 4/28/2022 | Corrections Issued | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 4/28/2022 | SGSOV Gas Company | PETER FOLLING |
| Final | 5/4/2022 | OK to Issue CofO | PETER FOLLING |