701 N TIGERTAIL ROAD 90049
Certificate Information: 701 N TIGERTAIL ROAD 90049
- Application / Permit
- 21047-20000-00628
- Plan Check / Job No.
- B21VN03364
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 61'-6" X 17'-0" POOL WITH 10'-0" X 7'-0" SPA PER ENGINEERING.
- Permit Issued
- Issued on 1/20/2022
- Issuing Office
- Current Status
- Issued on 1/20/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | COLIN LOREDO |
| Corrections Issued | 4/29/2021 | COLIN LOREDO |
| Quality Review Completed | 5/11/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/1/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 7/6/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 8/12/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 9/13/2021 | COLIN LOREDO |
| Plan Check Approved | 1/18/2022 | COLIN LOREDO |
| Issued | 1/20/2022 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 5/21/2021 | ANACANY HURTADO |
| GPI Written Notices | Cleared | 9/13/2021 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 9/13/2021 | COLIN LOREDO |
| Miscellaneous | Cleared | 9/13/2021 | COLIN LOREDO |
Contact Information
| Contractor | Building Solutions And Design; Lic. No.: 940604-B | 860 VIA DE LA PAZ SUITE D3E PACIFIC PALISADES, CA 90272 |
| Engineer | Cox,, Steven Jeffrey; Lic. No.: C48940 | 130 MAGELLAN ST THOUSAND OAKS, CA 91360 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 3/27/2025 | Partial Approval | KEVIN SARGSYAN |
| Pool Piping | 3/27/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Pre-Gunite | 3/27/2025 | Corrections Issued | KEVIN SARGSYAN |
| Rough-Electrical | 3/27/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Rough-Plumbing | 3/27/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Pool Piping | 4/11/2025 | Approved | KEVIN SARGSYAN |
| Pre-Gunite | 4/11/2025 | Approved | KEVIN SARGSYAN |
| Rough-Electrical | 4/11/2025 | Approved | KEVIN SARGSYAN |
| Rough-Plumbing | 4/11/2025 | Approved | KEVIN SARGSYAN |
| Deputy Other (see comments) | 12/12/2025 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Shotcrete | 12/12/2025 | Conditional Approval | KEVIN SARGSYAN |