10578 W HOLMAN AVE 90024

Certificate Information: 10578 W HOLMAN AVE 90024

Application / Permit
21047-20000-00595
Plan Check / Job No.
B21VN03143
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 32' X 16' IRREG SHAPED SWIMMING POOL AND 7' DIAMETER SPA PER LA STD PLAN #268
Permit Issued
Issued on 10/7/2021
Issuing Office
Current Status
CofO Issued on 5/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 COLIN LOREDO
Corrections Issued 3/20/2021 COLIN LOREDO
Applicant returned to address corrections 4/20/2021 LUIS RINCON
Applicant returned to address corrections 5/5/2021 LUIS RINCON
Plan Check Approved 9/29/2021 JEROME MAGAT PALMA
Issued 10/7/2021 APPLICANT
Building Plans Picked Up 10/21/2021 APPLICANT
CofO in Progress 5/25/2022 KENNETH NAGLE
CofO Issued 5/25/2022 DANIEL ORRANTE
Permit Finaled 5/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 8/27/2021 RIDWAN HARDY
Construction within easement Cleared 8/27/2021 RIDWAN HARDY

Contact Information

Contractor Sabby Aquascapes Design Group Inc; Lic. No.: 1078022-C53 23679 CALABASAS ROAD      CALABASAS, CA 91302
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/21/2021 Approved OGANES TARAKHCHYAN
Gas Piping or Gas Test 10/21/2021 Approved OGANES TARAKHCHYAN
Grounding or Bonding 10/21/2021 Approved OGANES TARAKHCHYAN
Pool Piping 10/21/2021 Approved OGANES TARAKHCHYAN
Pre-Gunite 10/21/2021 Approved OGANES TARAKHCHYAN
Rough-Electrical 10/21/2021 Approved OGANES TARAKHCHYAN
Rough-Plumbing 10/21/2021 Approved OGANES TARAKHCHYAN
Final 3/7/2022 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/7/2022 SGSOV Not Ready OGANES TARAKHCHYAN
Pool Equipment Noise Test 3/8/2022 Approved JUSTIN CURTIS
Pre-Inspection 3/8/2022 Corrections Issued OGANES TARAKHCHYAN
Final 3/11/2022 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Not Ready OGANES TARAKHCHYAN
Final 3/24/2022 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/24/2022 SGSOV Approved OGANES TARAKHCHYAN
Enclosure/Fence 4/19/2022 Corrections Issued KEVIN SARGSYAN
Final 4/19/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 4/27/2022 Approved EVAN COOPER
Enclosure/Fence 4/27/2022 Approved EVAN COOPER
Final 4/27/2022 Conditional Approval EVAN COOPER
Gunite 4/28/2022 Corrections Issued EVAN COOPER
Final 5/10/2022 Partial Approval OGANES TARAKHCHYAN
Rough-Plumbing 5/10/2022 Approved OGANES TARAKHCHYAN