8744 W SKYLINE DR 90046
Certificate Information: 8744 W SKYLINE DR 90046
- Application / Permit
- 21047-20000-00568
- Plan Check / Job No.
- B21VN03001
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 24' X 14' POOL PER ENGINEERING
- Permit Issued
- Issued on 12/25/2021
- Issuing Office
- Current Status
- CofO Issued on 12/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | CHON CHIO KUO |
| Corrections Issued | 4/21/2021 | CHON CHIO KUO |
| Quality Review Completed | 4/21/2021 | STEVEN KIM |
| Applicant returned to address corrections | 6/21/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 7/30/2021 | SELLA BENYAMIN |
| Plan Check Approved | 11/12/2021 | SELLA BENYAMIN |
| Issued | 12/25/2021 | APPLICANT |
| CofO in Progress | 12/7/2023 | RAUL BARAJAS |
| Permit Finaled | 12/7/2023 | DEROLD HAUFF |
| CofO Issued | 12/7/2023 | DEROLD HAUFF |
| Permit Finaled | 12/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/22/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2021 | DINAH GARIN |
| ZI | Cleared | 7/26/2021 | DANG NGUYEN |
Contact Information
| No Data Available. |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/24/2022 | Partial Inspection | RAUL BARAJAS |
| Pre-Inspection | 5/24/2022 | Partial Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 6/2/2022 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 6/10/2022 | Partial Approval | RAUL BARAJAS |
| Deputy Other (see comments) | 6/13/2022 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 6/13/2022 | No Access for Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 6/22/2022 | Approved | RAUL BARAJAS |
| Deputy Shotcrete | 6/23/2022 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 6/23/2022 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 8/2/2022 | Partial Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 8/5/2022 | Partial Approval | RAUL BARAJAS |
| Deputy Other (see comments) | 8/8/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Pre-Stress Concrete | 8/9/2022 | Conditional Approval | RAUL BARAJAS |
| Rough-Electrical | 9/19/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Rough-Plumbing | 9/19/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Rough-Electrical | 9/21/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Rough-Plumbing | 9/21/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Pre-Gunite | 1/26/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Other (see comments) | 2/2/2023 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Approved | RAUL BARAJAS |
| Grounding or Bonding | 2/8/2023 | Approved | RAUL BARAJAS |
| Pool Piping | 2/8/2023 | Approved | RAUL BARAJAS |
| Pre-Gunite | 2/8/2023 | Approved | RAUL BARAJAS |
| Rough-Electrical | 2/8/2023 | Partial Approval | RAUL BARAJAS |
| Rough-Plumbing | 2/8/2023 | Approved | RAUL BARAJAS |
| Deputy Shotcrete | 2/10/2023 | Conditional Approval | RAUL BARAJAS |
| Deck | 4/28/2023 | Approved | RAUL BARAJAS |
| Enclosure/Fence | 4/28/2023 | Approved | RAUL BARAJAS |
| Grounding or Bonding | 4/28/2023 | Approved | RAUL BARAJAS |
| Final | 7/11/2023 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Final | 7/25/2023 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 7/25/2023 | SGSOV Approved | RAUL BARAJAS |
| Final | 9/11/2023 | Corrections Issued | RAUL BARAJAS |
| Final | 11/28/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 12/7/2023 | OK to Issue CofO | RAUL BARAJAS |