12047 W MOUND VIEW PL 91604

Certificate Information: 12047 W MOUND VIEW PL 91604

Application / Permit
21047-20000-00566
Plan Check / Job No.
B21VN02994
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
REMODEL THE (E) POOL CHANGE THE SIZE TO 11'4" X 20'6" AND ADD A NEW SPA WITHIN THE EXISTING POOL PER LA STANDARD PLAN #268.
Permit Issued
Issued on 4/15/2021
Issuing Office
Current Status
CofO Issued on 11/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2021 APPLICANT
Assigned to Plan Check Engineer 3/15/2021 COLIN LOREDO
Corrections Issued 3/15/2021 COLIN LOREDO
Building Plans Picked Up 3/26/2021 APPLICANT
Plan Check Approved 4/15/2021 COLIN LOREDO
Issued 4/15/2021 APPLICANT
CofO in Progress 9/8/2021 ARAM AVEDISIAN
Permit Finaled 11/8/2021 MICHAEL SMITH
CofO Issued 11/8/2021 MICHAEL SMITH
Permit Finaled 11/8/2021 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Custom Derian Pools & Construction; Lic. No.: 977981-C53 21271 BURBANK BLVD #110      WOODLAND HILLS, CA 91367
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grounding or Bonding 5/13/2021 Partial Approval ARAM AVEDISIAN
Pre-Gunite 5/13/2021 Conditional Approval ARAM AVEDISIAN
Deputy Shotcrete 5/17/2021 Conditional Approval ARAM AVEDISIAN
Rough-Electrical 5/28/2021 Corrections Issued MICHAEL TEMPLE
Rough-Electrical 6/8/2021 Not Ready for Inspection THOMAS FINNILA
Pre-Inspection 6/25/2021 Partial Inspection ARAM AVEDISIAN
Deck 6/30/2021 Approved ARAM AVEDISIAN
Enclosure/Fence 8/3/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Final 9/2/2021 Not Ready for Inspection ARAM AVEDISIAN
Final 9/2/2021 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 9/2/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Final 9/8/2021 Approved ARAM AVEDISIAN
Final 9/8/2021 OK to Issue CofO ARAM AVEDISIAN
Special/Order Compliance 9/24/2021 Approved ARAM AVEDISIAN