870 E ROSE AVE 90291

Certificate Information: 870 E ROSE AVE 90291

Application / Permit
21047-20000-00524
Plan Check / Job No.
B21VN02793
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 12'x36' POOL AND SPA, ALL WORK PER LA CITY STANDARD PLAN #268
Permit Issued
Issued on 4/20/2021
Issuing Office
Current Status
CofO Issued on 12/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 SEAN SHAHMIRI
Corrections Issued 3/14/2021 SEAN SHAHMIRI
Applicant returned to address corrections 4/1/2021 LUISANGEL VALENZUELA
Issued 4/20/2021 APPLICANT
Building Plans Picked Up 4/22/2021 APPLICANT
CofO in Progress 11/30/2021 DAVID FEILER
Permit Finaled 12/16/2021 DANIEL ORRANTE
CofO Issued 12/16/2021 DANIEL ORRANTE
Permit Finaled 12/16/2021 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 3/22/2021 PABLO ESTRADA

Contact Information

Contractor Los Angeles Pool Builders Inc; Lic. No.: 857866-C53 9018 BALBOA BLVD SUITE 353      NORTHRIDGE, CA 91325
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 5/6/2021 Conditional Approval JOHNNY MIRANDA
Deputy Shotcrete 5/10/2021 Partial Approval DAVID HEINE
Deck 5/27/2021 Not Ready for Inspection JOHNNY MIRANDA
Grounding or Bonding 5/27/2021 Corrections Issued JOHNNY MIRANDA
Deck 6/2/2021 Approved JOHNNY MIRANDA
Grounding or Bonding 6/2/2021 Approved JOHNNY MIRANDA
Enclosure/Fence 6/15/2021 Corrections Issued JOHNNY MIRANDA
Enclosure/Fence 7/7/2021 Corrections Issued AMY COLIN
Enclosure/Fence 7/13/2021 Approved JOHNNY MIRANDA
Pool Equipment Noise Test 8/10/2021 Approved JAMES VORHIS
SGSOV-Seismic Gas S/O Valve 9/13/2021 SGSOV Not Required JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 10/8/2021 Approved JOHNNY MIRANDA
Final 10/8/2021 Partial Approval JOHNNY MIRANDA
Pre-Gunite 10/8/2021 Approved JOHNNY MIRANDA
Final 11/22/2021 OK to Issue CofO DAVID FEILER