22112 W RUNNYMEDE ST 91303
Certificate Information: 22112 W RUNNYMEDE ST 91303
- Application / Permit
- 21047-20000-00409
- Plan Check / Job No.
- B21VN02220
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16' X 21'-11" POOL PER STANDARD PLAN 254 WITH ENGINEERING DETAILS
- Permit Issued
- Issued on 4/19/2021
- Issuing Office
- Current Status
- CofO Issued on 11/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2021 | SELLA BENYAMIN |
| Plan Check Approved | 3/14/2021 | SELLA BENYAMIN |
| Building Plans Picked Up | 4/5/2021 | APPLICANT |
| Issued | 4/19/2021 | APPLICANT |
| CofO in Progress | 11/5/2021 | DAVID STEPANYAN |
| Permit Finaled | 11/5/2021 | JOHN JANSON |
| CofO Issued | 11/5/2021 | JOHN JANSON |
| Permit Finaled | 11/5/2021 | JOHN JANSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | A G Builders & Development Corp; Lic. No.: 959503-B | 7657 WINNETKA AVE #341 WINNETKA, CA 91306 |
| Engineer | Azizisefat,, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/26/2021 | Corrections Issued | DAVID STEPANYAN |
| Pre-Gunite | 4/26/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Pre-Gunite | 5/3/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 5/12/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Grounding or Bonding | 5/12/2021 | Corrections Issued | DAVID STEPANYAN |
| Pool Piping | 5/12/2021 | Corrections Issued | DAVID STEPANYAN |
| Pre-Gunite | 5/12/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Rough-Plumbing | 5/12/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 5/19/2021 | Approved | TROY SANDERS |
| Pre-Gunite | 5/19/2021 | Approved | TROY SANDERS |
| Rough-Plumbing | 5/19/2021 | Approved | TROY SANDERS |
| Grounding or Bonding | 6/14/2021 | Partial Approval | DAVID STEPANYAN |
| Pre-Gunite | 6/14/2021 | Approved | DAVID STEPANYAN |
| Enclosure/Fence | 6/23/2021 | Corrections Issued | DAVID STEPANYAN |
| Enclosure/Fence | 7/29/2021 | Not Ready for Inspection | PETER FOLLING |
| Enclosure/Fence | 8/10/2021 | Approved | PETER FOLLING |
| Equipment Noise Level | 9/3/2021 | Approved | ROBERT GOLD |
| Final | 10/27/2021 | No Access for Inspection | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2021 | SGSOV Not Ready | DAVID STEPANYAN |
| Final | 11/3/2021 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 11/3/2021 | SGSOV Not Required | DAVID STEPANYAN |
| ELECTRICAL-Final | 11/4/2021 | Approved | DAVID STEPANYAN |
| Final | 11/4/2021 | OK to Issue CofO | DAVID STEPANYAN |