1825 S PANDORA AVE 90025

Certificate Information: 1825 S PANDORA AVE 90025

Application / Permit
21047-20000-00403
Plan Check / Job No.
B21VN02186
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
Apartment
Primary Use
(4) Pool/Spa - Public
Work Description
NEW APT SPA (12'-0"x14'-0") per standard plan #268
Permit Issued
Issued on 5/17/2021
Issuing Office
Current Status
CofO Issued on 7/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2021 APPLICANT
Disabled Access Plans Picked Up 3/15/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 MOHAMMAD ESMAILI
Corrections Issued 3/23/2021 MOHAMMAD ESMAILI
Quality Review Completed 4/1/2021 OMID HEDAYAT
Plan Check Approved 5/17/2021 MOHAMMAD ESMAILI
Issued 5/17/2021 APPLICANT
CofO in Progress 7/19/2023 DERRICK SPENCER
Permit Finaled 7/24/2023 DAVID TSAU
CofO Issued 7/24/2023 DAVID TSAU
Permit Finaled 7/24/2023 DAVID TSAU

Permit Application Clearance Information

DAS Clearance Cleared 4/6/2021 NORLITO MEDRANO
ZA Case Cleared 4/23/2021 LAUREN PADICK
Public Swimming Pool approval Cleared 5/17/2021 LACDHS APPROVED

Contact Information

Contractor Mission Pools Of Escondido; Lic. No.: 326760-C53 755 WEST GRAND AVENUE      ESCONDIDO, CA 92025
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Rough-Electrical 7/23/2021 Partial Inspection PAUL DAVIDSON
METHANE-Rough 10/4/2022 Not Ready for Inspection DERRICK SPENCER
Pre-Gunite 10/4/2022 Not Ready for Inspection DERRICK SPENCER
METHANE-Rough 10/7/2022 Not Ready for Inspection DERRICK SPENCER
Pre-Gunite 10/7/2022 Not Ready for Inspection DERRICK SPENCER
Special/Order Compliance 10/12/2022 Not Ready for Inspection DERRICK SPENCER
METHANE-Rough 10/18/2022 Approved DERRICK SPENCER
Pre-Gunite 10/18/2022 Approved DERRICK SPENCER
Deputy Shotcrete 10/19/2022 Approved DERRICK SPENCER
Rough-Electrical 4/18/2023 Not Ready for Inspection DERRICK SPENCER
Enclosure/Fence 4/24/2023 Approved DERRICK SPENCER
PLUMBING-Final 5/30/2023 Not Ready for Inspection DERRICK SPENCER
PLUMBING-Final 6/2/2023 Not Ready for Inspection DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 7/13/2023 Approved DERRICK SPENCER
Final 7/13/2023 Not Ready for Inspection DERRICK SPENCER
METHANE-Barrier 7/13/2023 Approved DERRICK SPENCER
METHANE-Subgrade 7/13/2023 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 7/13/2023 SGSOV Approved DERRICK SPENCER
Final 7/17/2023 OK to Issue CofO DERRICK SPENCER