22021 W CANTLAY ST 91303
Certificate Information: 22021 W CANTLAY ST 91303
- Application / Permit
- 21047-20000-00369
- Plan Check / Job No.
- B21VN01994
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL (14'-0"x26'-0") AND SPA (6'-0"x6'-0")
- Permit Issued
- Issued on 4/13/2021
- Issuing Office
- Current Status
- CofO Issued on 9/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/6/2021 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 3/12/2021 | RARES BODEA |
| Building Plans Picked Up | 3/16/2021 | APPLICANT |
| Plan Check Approved | 4/7/2021 | MOHAMMAD ESMAILI |
| Issued | 4/13/2021 | APPLICANT |
| CofO in Progress | 3/15/2022 | DAVID SCANTLIN |
| Permit Finaled | 9/12/2022 | DANIEL ORRANTE |
| CofO Issued | 9/12/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/12/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/2/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Lax Home Inc; Lic. No.: 1063552-B | 15021 VENTURA BLVD STE 810 SHERMAN OAKS, CA 91403 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/4/2021 | Corrections Issued | DAVID STEPANYAN |
| Gas Piping or Gas Test | 5/4/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Pool Piping | 5/4/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Pre-Gunite | 5/4/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Pre-Inspection | 5/4/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Rough-Electrical | 5/4/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Rough-Plumbing | 5/4/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 7/12/2021 | Approved | DAVID STEPANYAN |
| Gas Piping or Gas Test | 7/12/2021 | Approved | DAVID STEPANYAN |
| Grounding or Bonding | 7/12/2021 | Partial Approval | DAVID STEPANYAN |
| Pool Piping | 7/12/2021 | Approved | DAVID STEPANYAN |
| Pre-Gunite | 7/12/2021 | Approved | DAVID STEPANYAN |
| Pre-Inspection | 7/12/2021 | Partial Inspection | DAVID STEPANYAN |
| Rough-Electrical | 7/12/2021 | Partial Approval | DAVID STEPANYAN |
| Deputy Shotcrete | 7/14/2021 | Conditional Approval | DAVID STEPANYAN |
| Deck | 8/9/2021 | Approved | DAVID STEPANYAN |
| Grounding or Bonding | 8/9/2021 | Partial Approval | DAVID STEPANYAN |
| Enclosure/Fence | 8/24/2021 | Corrections Issued | DAVID STEPANYAN |
| Enclosure/Fence | 8/26/2021 | Approved | DAVID STEPANYAN |
| Equipment Noise Level | 9/13/2021 | Approved | ALFREDO FLORES |
| Pool Equipment Noise Test | 9/13/2021 | Approved | ALFREDO FLORES |
| Final | 2/10/2022 | Corrections Issued | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 2/10/2022 | SGSOV Approved | JEFFREY PARD |
| Final | 2/22/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 3/14/2022 | OK to Issue CofO | DAVID SCANTLIN |