890 N LINDA FLORA DR 90049

Certificate Information: 890 N LINDA FLORA DR 90049

Application / Permit
21047-20000-00357
Plan Check / Job No.
B21VN01926
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) POOL (46'-4" X 21'-4") & SPA (7'-6" X 10'-2") PER ENG'R DESIGN
Permit Issued
Issued on 3/22/2021
Issuing Office
Current Status
CofO Issued on 8/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2021 APPLICANT
Assigned to Plan Check Engineer 2/25/2021 NILOOFAR MEHRAIN
Corrections Issued 3/2/2021 NILOOFAR MEHRAIN
Quality Review Completed 3/2/2021 CHON CHIO KUO
Building Plans Picked Up 3/2/2021 APPLICANT
Plan Check Approved 3/22/2021 NILOOFAR MEHRAIN
Issued 3/22/2021 APPLICANT
CofO in Progress 8/22/2022 CARLOS MATAMOROS
Permit Finaled 8/26/2022 DANIEL ORRANTE
CofO Issued 8/26/2022 DANIEL ORRANTE
Permit Finaled 8/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/27/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Shain Development Inc; Lic. No.: 937795-B 832 LAS LOMAS AVE      PACIFIC PALISADES, CA 90272
Engineer Guivatchian,, Mohammad; Lic. No.: C36510 4720 DEGOVIA AVENUE      WOODLAND HILLS, CA 91364
Geologist Feffer,, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/13/2021 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/17/2021 Approved CARLOS MATAMOROS
Grounding or Bonding 5/17/2021 Approved CARLOS MATAMOROS
Pre-Gunite 5/17/2021 Approved CARLOS MATAMOROS
Rough-Plumbing 5/17/2021 Approved CARLOS MATAMOROS
Deputy Shotcrete 5/25/2021 Conditional Approval CARLOS MATAMOROS
Enclosure/Fence 12/6/2021 Corrections Issued CARLOS MATAMOROS
Enclosure/Fence 12/8/2021 Approved CARLOS MATAMOROS
Pool/Spa Cover 12/8/2021 Corrections Issued CARLOS MATAMOROS
Pool Equipment Noise Test 2/16/2022 Approved JUSTIN CURTIS
Final 4/28/2022 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 4/28/2022 SGSOV Not Ready CHRISTOPHER WILSON
Final 4/29/2022 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 5/6/2022 Approved CARLOS MATAMOROS
Final 5/6/2022 OK to Issue CofO CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 5/6/2022 SGSOV Approved CARLOS MATAMOROS